Skip to main content

Borinquen I: Costa Rica’s $100 Million Geothermal Bet Moves From Delay to Delivery

Borinquen I: Costa Rica’s Geothermal Revival Takes Concrete Form



ICE Awards $100 Million Electromechanical Contract as Project Exceeds 55% Completion

On June 4, 2026, the Instituto Costarricense de Electricidad (ICE) awarded a contract for the design, supply, supervision, testing, and commissioning of electromechanical generation equipment for the Borinquen I Geothermal Project. The transaction is valued at approximately $100 million.

The award marks a definitive turning point for a project that spent years in institutional limbo.


The Contract Scope

The electromechanical equipment package encompasses three core components:

The generating unit – driven by volcanic steam
Associated systems and equipment
The cooling tower

ICE will formalize the contract in the second half of 2026. Construction of the machine house is scheduled to begin in July 2027.

This is not a speculative timeline. The contract award is complete. The sequencing is now fixed.


Project Status: Beyond Halfway

Borinquen I currently stands at over 55 percent total works completion. The plant employs more than 500 people. Located in Liberia, Guanacaste, it will become Costa Rica’s eighth geothermal facility upon commissioning.

The projected completion date is early 2030.

Fifty-five percent completion with four years remaining suggests the remaining work is disproportionately electromechanical – the phase now being contracted. Civil works are substantially advanced. The critical path has shifted to equipment fabrication, delivery, installation, and commissioning.


Capacity and System Role

Borinquen I will contribute 55 megawatts of firm capacity to Costa Rica’s national electrical system.

The term “firm capacity” is material. Unlike wind or solar generation, which depend on weather conditions, geothermal provides baseload power – continuous, predictable, and dispatchable on demand. For a country that has operated on over 98 percent renewable electricity for years, the marginal value of each additional firm megawatt increases as intermittent sources grow.

Fifty-five megawatts is not marginal. It represents meaningful baseload reinforcement.


The Delay: What Happened and When

Marco Acuña, president of Grupo ICE, stated publicly that Borinquen suffered postponements under past administrations, specifically noting that its entry into operation was shifted in 2018.

The statement is precise: the delay occurred in 2018, not as a result of technical failure but of administrative decision. The project was effectively displaced.

The current government (2022–2026) revived the project. Acuña’s framing is unambiguous: Borinquen is “essential to meet the country’s electricity demand and its future energy needs.”

This is not promotional language. It is a statement of necessity. Costa Rica’s demand trajectory has not paused. The postponement created a gap that must now be closed.

Costa Rica’s Geothermal Standing

Costa Rica is a continental power in geothermal energy production, surpassed only by Mexico and the United States.

The country has accumulated more than 50 years of resource study. This is not recent enthusiasm. Systematic investigation began decades before the first plant came online.

Miravalles I – Costa Rica’s first geothermal plant – entered operation in 1994. That is 32 years before this contract award. The learning curve has been long, incremental, and institutionalized within ICE.

What the Electromechanical Award Signals

Three signals are embedded in this announcement:

First, ICE has moved from planning to procurement. The project is no longer awaiting approvals or financing. The $100 million commitment is execution capital.

Second, the 2030 completion target is credible. The contract signing in late 2026, machine house construction beginning July 2027, and early 2030 operation suggest a 42-month electromechanical phase. For a 55 MW geothermal plant, that is realistic.

Third, the project has survived political transition. The 2022–2026 government revived it. The contract signature will occur after that government leaves office – in the second half of 2026 – meaning the incoming administration will inherit an executed contract, not a proposal.


Employment and Local Impact

More than 500 people currently work on Borinquen I. That figure reflects civil works and early site preparation.

Electromechanical installation typically requires specialized labor – turbine and generator technicians, control systems engineers, high-voltage electricians. The workforce composition will shift. But total employment may not decline; peak construction employment often occurs during equipment installation and commissioning.

The plant is in Liberia. That geography matters. Guanacaste has been a wind and solar corridor. Geothermal adds a different profile: higher capacity factor, smaller physical footprint per megawatt, and continuous operation.


Comparative Context

Mexico and the United States lead the continent in geothermal generation. Costa Rica holds third place – not by accident but by sustained policy and state investment.

Unlike El Salvador (another geothermal user with a smaller economy) or Nicaragua (which has development potential but less installed capacity), Costa Rica has integrated geothermal into a near-total renewable matrix. This is unusual globally. Most countries with high renewable penetration rely heavily on hydroelectric storage or natural gas backup. Costa Rica uses geothermal as firm, carbon-free baseload.

The country has studied the resource for over five decades. That timescale exceeds commercial operations of most renewable technologies. Geothermal exploration is expensive and risky. State absorption of that risk – through ICE – enabled the learning curve.

Operational Timeline Realities

The statement projects conclusion “at the beginning of 2030.” That is approximately 42 months from the July 2027 machine house start date.

Geothermal electromechanical installation follows a known sequence:

1. Turbine and generator foundation setting
2. Steam gathering system connection
3. Turbine installation and alignment
4. Generator installation
5. Cooling tower construction
6. Control system integration
7. Individual component testing
8. System integration testing
9. Steam admission and synchronization
10. Commercial operation

The 2030 target assumes no major supply chain disruptions. The $100 million contract size suggests a single supplier or consortium – typical for geothermal turbogenerators. Procurement is now complete. Fabrication lead times for large turbines range from 18 to 30 months. A late 2026 contract signing puts delivery in 2028–2029, aligning with the July 2027 civil start.

What Is Not in the Announcement

The press release does not specify:

· The winning contractor or consortium
· Whether the turbine is back-pressure or condensing
· The geothermal fluid chemistry and its implications for materials selection
· Reinjection well status
· Steam field development progress
· Grid connection point and transmission upgrades required

These are not omissions of secrecy but of scope. The announcement is a procurement update, not a technical datasheet.

The absence of contractor name is notable. Adjudication occurred June 4, 2026. The announcement was published June 10, 2026. Contract signing is scheduled for second half of 2026. That gap may reflect final commercial negotiations or conditional approvals.


Institutional Continuity

ICE is executing this project as a state institution. The announcement carries the institutional seal, not a political party’s branding. The press contact emails use the @ice.go.cr domain. The authorization note permits reproduction citing the original source.

This is worth noting because geothermal development requires long-term institutional memory. Costa Rica’s 50-plus years of study reside within ICE. Miravalles I’s 1994 commissioning was an ICE achievement. The utility has operated multiple geothermal plants continuously for three decades. The operational competence is proven.

The 2018 Delay Revisited

Acuña’s reference to the 2018 postponement is precise political language. He does not name administrations. He says “past administrations” and notes the entry was “shifted” from 2018.

The implication: the project was ready or nearing readiness in 2018. It did not proceed. The current government reversed that decision.

For context, 2018 was the first year of the Carlos Alvarado administration. The previous administration (Luis Guillermo Solís, 2014–2018) would have overseen planning that targeted 2018 operation. The delay occurred at the transition or shortly after.

Acuña’s statement attributes revival to the 2022–2026 government. That places the political responsibility clearly. The project is now beyond reversal without contract breach.


Why Firm Capacity Matters Now

Costa Rica’s electrical demand has grown. Electric vehicle adoption is accelerating. The transportation sector is progressively electrifying. Industrial demand does not pause.

Intermittent renewables – wind and solar – produce when resources are available. Geothermal produces when needed. The 55 MW from Borinquen I replaces the need for thermal backup (imported or fossil-based) during periods of low hydro reservoir levels or low wind.

The phrase “firm capacity” in the announcement is technical. It means the 55 MW can be counted on for system planning. That is different from nameplate capacity of solar or wind, which requires derating for availability.


2030: The Completion Year

Early 2030 is the target. That is four years from the contract award. The timeline is not aggressive by geothermal standards. Typical development cycles from exploration to operation range 6–10 years. Borinquen I has already completed exploration, drilling, resource confirmation, and substantial civil works.

The remaining work is industrial, not geological. No resource uncertainty remains. The steam is there. The question is only engineering and construction execution.

Conclusion

The Borinquen I electromechanical contract award is not a milestone. It is a decision. ICE has committed $100 million to a specific supplier for a specific scope. The project is 55 percent complete. The machine house will start in July 2027. Commercial operation is scheduled for early 2030.

Costa Rica’s geothermal history – 50 years of study, third place on the continent, Miravalles I online since 1994 – provides the institutional substrate. The 2018 postponement was a political choice. The 2022–2026 revival was also a political choice. The contract signature in late 2026 will be an institutional execution.

Fifty-five megawatts of firm capacity. Eight geothermal plants. Five hundred current jobs. One hundred million dollars committed. Four years to completion.

Borinquen I is no longer a project under consideration. It is a project under construction.


Source : Groupo ICE

Connect with us:LinkedIn, X

Comments

Hot Topics

Blowout at Cape Station: Fervo Energy’s First Major Crisis After Blockbuster IPO

Just weeks after a record-breaking IPO, the flagship project of the "geothermal unicorn" faces its first major operational crisis. By : Robert Buluma   Beaver County, Utah – The morning of May 27, 2026, began like any other at the Cape Station construction site in rural Utah. Workers for Fervo Energy, the newly public darling of the renewable energy world, were engaged in the complex task of drilling deep into the Earth’s crust to unlock what the company promised would be the future of 24/7 clean power. But by the afternoon, the routine had turned into a crisis. The site had experienced a blowout—an uncontrolled release of fluid or pressure from a well. For any energy company, a blowout is a serious matter. For Fervo Energy, which had just raised $1.89 billion in a blockbuster Nasdaq debut two weeks prior, it represents an immediate stress test of its technology, its safety protocols, and its $7.7 billion market valuation. While the well has since been contained and no injur...

Enhanced Geothermal Systems Financing Hurdles

The Heat Beneath: Why Enhanced Geothermal Systems Can't Get Financing—And What It Will Take to Change That By : Robert Buluma Introduction: The Paradox of Boundless Energy Beneath our feet lies an energy source so vast that capturing just a fraction of it could power civilization for millennia. More than five terawatts of heat resources exist beneath the United States alone—enough to meet the electricity needs of the entire world. Enhanced Geothermal Systems (EGS), which circulate water through engineered fractures in deep hot rock, promise to unlock this resource nearly anywhere on the planet, not just in volcanic hotspots. The technology is improving faster than almost anyone expected. Costs are falling. The fossil fuel industry's drilling expertise is being repurposed. And yet, for all its promise, EGS remains stuck in a financial no-man's-land—too big for venture capital, too risky for traditional lenders, and too unfamiliar for the infrastructure investors who could tr...

The Heat Beneath Our Feet: How Canada’s First National Geothermal Roadmap Could Redefine Clean Energy

The Heat Beneath Our Feet: Canada Invests in First National Geothermal Energy Roadmap By: Robert Buluma   Image: The Eavor Wonder,  something amazing 👏  Calgary, Alberta – June 11, 2026 – In a move that signals a significant shift toward diversifying its clean energy portfolio, the Government of Canada has officially invested in its first national roadmap for deep geothermal energy. The announcement, made today by the Honourable Tim Hodgson, Minister of Energy and Natural Resources , marks a pivotal moment for a country better known for its oil sands and hydroelectric dams than for harnessing the heat of the Earth’s crust. With a conditional investment of $468,000 through Natural Resources Canada’s Energy Innovation Program , the government is backing the Canadian Deep Geothermal Roadmap project. Led by the Canadian Deep Geothermal Coalition and supported by the  Cascade Institute as the secretariat, this initiative aims to create a cohesive, evidence-based strate...

Rodatherm Energy: The Refrigerant Gambit

By: Robert Buluma   Rodatherm Energy has done something no other geothermal startup has attempted at commercial scale: swapped water for refrigerant in a closed-loop system. The claim is 50% higher thermal efficiency than water-based binary cycles, achieved by circulating a proprietary phase-change fluid through a fully cased, pressurized wellbore. The company emerged from stealth in September 2025 with a $38 million Series A—the largest first venture raise in geothermal history. Lead investor Evok Innovations was joined by Toyota Ventures, TDK Ventures, and the Grantham Foundation. The engineering thesis is elegant. The execution risks are significant. This is an Alphaxioms examination of both. II. The Thermodynamic Distinction Every geothermal company you've covered moves heat using water or steam. Rodatherm moves heat using a fluid that boils and condenses inside the wellbore. In a conventional closed-loop water system (Eavor's model), water circulates as a single-phase liq...

Mazama Energy Newberry Superhot Geothermal Breakthrough Reshapes Clean Energy

Mazama Energy’s Superhot Rock Vision Redefines Global Geothermal Power By Robert Buluma   The geothermal industry is entering a new era, and one company is pushing the boundaries of what was once considered technically impossible. Mazama Energy has ignited global attention after revealing extraordinary progress at its Newberry geothermal site in central Oregon, where it reportedly achieved temperatures of 331°C in an enhanced geothermal system environment. For an industry accustomed to operating within the 150°C to 300°C range, this milestone is more than impressive — it signals the possible beginning of a technological transformation capable of reshaping the future of clean baseload power. For decades, geothermal energy has quietly remained one of the most reliable renewable energy resources on Earth. Unlike solar and wind, geothermal power does not depend on weather conditions, sunlight, or seasonal variability. It delivers continuous electricity twenty-four hours a day, seven ...

The Retrofit Revolution: How GreenFire Energy Is Turning Abandoned Oil & Geothermal Wells Into Continuous Clean Power Without New Drilling

The Retrofit Revolution: How GreenFire Energy Is Unlocking Geothermal Power Without Drilling a Single New Well By: Robert Buluma   While much of the geothermal energy sector has been focused on breakthrough drilling techniques—deeper wells, hotter reservoirs, and complex engineered systems—a quieter revolution has been unfolding in the background. Instead of chasing entirely new subsurface frontiers, one company has chosen a radically simpler question: What if the answer was already in the ground? GreenFire Energy is advancing a retrofit-first geothermal strategy that targets one of the most overlooked opportunities in the global energy transition: existing wells that are underperforming, depleted, or completely abandoned. Rather than drilling new holes into the Earth, the company is reusing the infrastructure that already exists—turning stranded assets into continuous sources of clean, baseload electricity. This approach is not just technically elegant. It may also be one of ...

"Below the Surface: How Baker Hughes is Drilling the 24/7 Clean Energy Solution"

Below the Surface: How Baker Hughes is Drilling the 24/7 Clean Energy Solution By: Robert Buluma   The geothermal era has arrived — and   Baker Hughes is holding the drill. While much of the energy world remains fixated on LNG exports and offshore wind, a quieter revolution is taking place beneath our feet. Baker Hughes (BKR) , the Houston-based energy technology giant, has assembled what may be the most comprehensive geothermal partnership network in the industry — positioning itself as the go-to industrial executor for next-generation geothermal power. In 2026 alone, the company has locked in strategic collaborations spanning three continents, from the deserts of Saudi Arabia to the outback of Australia and the high-heat basins of the American West. The common thread? Baker Hughes is applying a century of oil and gas drilling expertise to unlock geothermal energy at industrial scale — and the data center boom is providing the perfect market catalyst. The Strategy: "G...

Sage Geosystems: Turning Underground Pressure Into 24/7 Power

Sage Geosystems : The Geothermal Startup That Turns Pressure Into Power By: Robert Buluma Most conversations about advanced geothermal circle around the same question: How do you extract heat from dry rock? Sage Geosystems started with a different question: What if the Earth could do most of the work for you? Based in Houston, Sage has quietly built a technology stack that treats the subsurface not just as a heat source, but as a pressure vessel. Their system captures heat and mechanical energy, stores energy underground like a battery, and uses a fraction of the surface pumping that conventional geothermal requires. This article focuses entirely on Sage , how their technology works, what makes it genuinely different, and where the blind spots still are. Part I: The Core Innovation , Pressure Geothermal Sage's foundational insight is simple but powerful: deep hot rock isn't just hot. It's also under immense natural pressure. Traditional geothermal systems ignore that pre...

Project Obsidian: Unlocking Superhot Geothermal Power from Deep Earth

Quaise Energy and the Dawn of Superhot Geothermal Power in Oregon By: Robert Buluma Inside Project Obsidian and the Future of Deep Earth Energy The global energy transition has long been defined by solar panels on rooftops, wind turbines across plains, and batteries reshaping grids. Yet beneath all these familiar technologies, another contender is quietly emerging—one that does not depend on weather, daylight, or even surface conditions at all. It comes from deep within the Earth itself, from rock so hot it behaves almost like a molten energy reservoir. That is the frontier where Quaise Energy is now operating. In Oregon, the company is developing what could become the world’s first superhot geothermal power plant under its ambitious initiative known as Project Obsidian . If successful, it could mark a fundamental shift in how humanity produces clean, continuous electricity—moving from shallow geothermal pockets to tapping heat sources several kilometers beneath the Earth’s surfac...

The XGS Energy Heat Sponge Solves Geothermal's Biggest Problem

The XGS Energy Heat Sponge Solves Geothermal's Biggest Problem I mage: A californian XGS well pad Imagine drilling a hole into the Earth’s hot crust  but instead of simply dropping in a pipe and hoping for the best, you paint the inside of that hole with a magic material that soaks up heat like a sponge soaks up water. Then you seal it, circulate a fluid, and generate clean, firm electricity  24/7, no fracking, no water consumption, no earthquakes. That’s not science fiction. That’s XGS Energy . While most of the geothermal world has been chasing fracked reservoirs or massive drilling rigs, XGS quietly built a prototype, ran it for over 3,000 hours in one of the harshest geothermal environments on Earth, and landed a 150 MW deal with Meta – enough to power tens of thousands of homes or a massive data center campus. This is the story of a technology that might be the most elegant, low-risk, and capital-efficient path to scalable geothermal power. Let’s dig in. Part 1: The Pro...