Skip to main content

Just In

Mijnwater Starts Terhoevenderweg Drilling for New 634-Meter Heat Source in Heerlen

Mijnwater starts drilling for new heat source on Terhoevenderweg in Heerlen New source expands Parkstad’s district heating and cooling network Mijnwater has started drilling work for a new heat source at Terhoevenderweg in Heerlen, marking another important step in the expansion of its sustainable heating and cooling network in Parkstad. After a period of preparation, work began this week and is expected to continue for three to four weeks. Because the operation must be completed safely and efficiently, the drilling is taking place 24 hours a day, seven days a week. The project is part of Mijnwater’s broader effort to strengthen a low-carbon energy system for the region. The new source will tap warm groundwater in a former mine passage deep underground and feed that energy into the company’s network. For Heerlen and the surrounding area, this means further development of a district energy system that draws value from the region’s mining past while supporting a more sustainable energy ...

Borinquen I: Costa Rica’s $100 Million Geothermal Bet Moves From Delay to Delivery

Borinquen I: Costa Rica’s Geothermal Revival Takes Concrete Form



ICE Awards $100 Million Electromechanical Contract as Project Exceeds 55% Completion

On June 4, 2026, the Instituto Costarricense de Electricidad (ICE) awarded a contract for the design, supply, supervision, testing, and commissioning of electromechanical generation equipment for the Borinquen I Geothermal Project. The transaction is valued at approximately $100 million.

The award marks a definitive turning point for a project that spent years in institutional limbo.


The Contract Scope

The electromechanical equipment package encompasses three core components:

The generating unit – driven by volcanic steam
Associated systems and equipment
The cooling tower

ICE will formalize the contract in the second half of 2026. Construction of the machine house is scheduled to begin in July 2027.

This is not a speculative timeline. The contract award is complete. The sequencing is now fixed.


Project Status: Beyond Halfway

Borinquen I currently stands at over 55 percent total works completion. The plant employs more than 500 people. Located in Liberia, Guanacaste, it will become Costa Rica’s eighth geothermal facility upon commissioning.

The projected completion date is early 2030.

Fifty-five percent completion with four years remaining suggests the remaining work is disproportionately electromechanical – the phase now being contracted. Civil works are substantially advanced. The critical path has shifted to equipment fabrication, delivery, installation, and commissioning.


Capacity and System Role

Borinquen I will contribute 55 megawatts of firm capacity to Costa Rica’s national electrical system.

The term “firm capacity” is material. Unlike wind or solar generation, which depend on weather conditions, geothermal provides baseload power – continuous, predictable, and dispatchable on demand. For a country that has operated on over 98 percent renewable electricity for years, the marginal value of each additional firm megawatt increases as intermittent sources grow.

Fifty-five megawatts is not marginal. It represents meaningful baseload reinforcement.


The Delay: What Happened and When

Marco Acuña, president of Grupo ICE, stated publicly that Borinquen suffered postponements under past administrations, specifically noting that its entry into operation was shifted in 2018.

The statement is precise: the delay occurred in 2018, not as a result of technical failure but of administrative decision. The project was effectively displaced.

The current government (2022–2026) revived the project. Acuña’s framing is unambiguous: Borinquen is “essential to meet the country’s electricity demand and its future energy needs.”

This is not promotional language. It is a statement of necessity. Costa Rica’s demand trajectory has not paused. The postponement created a gap that must now be closed.

Costa Rica’s Geothermal Standing

Costa Rica is a continental power in geothermal energy production, surpassed only by Mexico and the United States.

The country has accumulated more than 50 years of resource study. This is not recent enthusiasm. Systematic investigation began decades before the first plant came online.

Miravalles I – Costa Rica’s first geothermal plant – entered operation in 1994. That is 32 years before this contract award. The learning curve has been long, incremental, and institutionalized within ICE.

What the Electromechanical Award Signals

Three signals are embedded in this announcement:

First, ICE has moved from planning to procurement. The project is no longer awaiting approvals or financing. The $100 million commitment is execution capital.

Second, the 2030 completion target is credible. The contract signing in late 2026, machine house construction beginning July 2027, and early 2030 operation suggest a 42-month electromechanical phase. For a 55 MW geothermal plant, that is realistic.

Third, the project has survived political transition. The 2022–2026 government revived it. The contract signature will occur after that government leaves office – in the second half of 2026 – meaning the incoming administration will inherit an executed contract, not a proposal.


Employment and Local Impact

More than 500 people currently work on Borinquen I. That figure reflects civil works and early site preparation.

Electromechanical installation typically requires specialized labor – turbine and generator technicians, control systems engineers, high-voltage electricians. The workforce composition will shift. But total employment may not decline; peak construction employment often occurs during equipment installation and commissioning.

The plant is in Liberia. That geography matters. Guanacaste has been a wind and solar corridor. Geothermal adds a different profile: higher capacity factor, smaller physical footprint per megawatt, and continuous operation.


Comparative Context

Mexico and the United States lead the continent in geothermal generation. Costa Rica holds third place – not by accident but by sustained policy and state investment.

Unlike El Salvador (another geothermal user with a smaller economy) or Nicaragua (which has development potential but less installed capacity), Costa Rica has integrated geothermal into a near-total renewable matrix. This is unusual globally. Most countries with high renewable penetration rely heavily on hydroelectric storage or natural gas backup. Costa Rica uses geothermal as firm, carbon-free baseload.

The country has studied the resource for over five decades. That timescale exceeds commercial operations of most renewable technologies. Geothermal exploration is expensive and risky. State absorption of that risk – through ICE – enabled the learning curve.

Operational Timeline Realities

The statement projects conclusion “at the beginning of 2030.” That is approximately 42 months from the July 2027 machine house start date.

Geothermal electromechanical installation follows a known sequence:

1. Turbine and generator foundation setting
2. Steam gathering system connection
3. Turbine installation and alignment
4. Generator installation
5. Cooling tower construction
6. Control system integration
7. Individual component testing
8. System integration testing
9. Steam admission and synchronization
10. Commercial operation

The 2030 target assumes no major supply chain disruptions. The $100 million contract size suggests a single supplier or consortium – typical for geothermal turbogenerators. Procurement is now complete. Fabrication lead times for large turbines range from 18 to 30 months. A late 2026 contract signing puts delivery in 2028–2029, aligning with the July 2027 civil start.

What Is Not in the Announcement

The press release does not specify:

· The winning contractor or consortium
· Whether the turbine is back-pressure or condensing
· The geothermal fluid chemistry and its implications for materials selection
· Reinjection well status
· Steam field development progress
· Grid connection point and transmission upgrades required

These are not omissions of secrecy but of scope. The announcement is a procurement update, not a technical datasheet.

The absence of contractor name is notable. Adjudication occurred June 4, 2026. The announcement was published June 10, 2026. Contract signing is scheduled for second half of 2026. That gap may reflect final commercial negotiations or conditional approvals.


Institutional Continuity

ICE is executing this project as a state institution. The announcement carries the institutional seal, not a political party’s branding. The press contact emails use the @ice.go.cr domain. The authorization note permits reproduction citing the original source.

This is worth noting because geothermal development requires long-term institutional memory. Costa Rica’s 50-plus years of study reside within ICE. Miravalles I’s 1994 commissioning was an ICE achievement. The utility has operated multiple geothermal plants continuously for three decades. The operational competence is proven.

The 2018 Delay Revisited

Acuña’s reference to the 2018 postponement is precise political language. He does not name administrations. He says “past administrations” and notes the entry was “shifted” from 2018.

The implication: the project was ready or nearing readiness in 2018. It did not proceed. The current government reversed that decision.

For context, 2018 was the first year of the Carlos Alvarado administration. The previous administration (Luis Guillermo Solís, 2014–2018) would have overseen planning that targeted 2018 operation. The delay occurred at the transition or shortly after.

Acuña’s statement attributes revival to the 2022–2026 government. That places the political responsibility clearly. The project is now beyond reversal without contract breach.


Why Firm Capacity Matters Now

Costa Rica’s electrical demand has grown. Electric vehicle adoption is accelerating. The transportation sector is progressively electrifying. Industrial demand does not pause.

Intermittent renewables – wind and solar – produce when resources are available. Geothermal produces when needed. The 55 MW from Borinquen I replaces the need for thermal backup (imported or fossil-based) during periods of low hydro reservoir levels or low wind.

The phrase “firm capacity” in the announcement is technical. It means the 55 MW can be counted on for system planning. That is different from nameplate capacity of solar or wind, which requires derating for availability.


2030: The Completion Year

Early 2030 is the target. That is four years from the contract award. The timeline is not aggressive by geothermal standards. Typical development cycles from exploration to operation range 6–10 years. Borinquen I has already completed exploration, drilling, resource confirmation, and substantial civil works.

The remaining work is industrial, not geological. No resource uncertainty remains. The steam is there. The question is only engineering and construction execution.

Conclusion

The Borinquen I electromechanical contract award is not a milestone. It is a decision. ICE has committed $100 million to a specific supplier for a specific scope. The project is 55 percent complete. The machine house will start in July 2027. Commercial operation is scheduled for early 2030.

Costa Rica’s geothermal history – 50 years of study, third place on the continent, Miravalles I online since 1994 – provides the institutional substrate. The 2018 postponement was a political choice. The 2022–2026 revival was also a political choice. The contract signature in late 2026 will be an institutional execution.

Fifty-five megawatts of firm capacity. Eight geothermal plants. Five hundred current jobs. One hundred million dollars committed. Four years to completion.

Borinquen I is no longer a project under consideration. It is a project under construction.


Source : Groupo ICE

Connect with us:LinkedIn, X

Comments

Popular posts from this blog

EGS Market Size and Investment Outlook

Enhanced Geothermal Systems (EGS) Market Size and Investment Outlook to 2034 Enhanced Geothermal Systems are at an inflection point. For years, EGS sat in the “promising but pre‑commercial” category of clean technologies, constrained by drilling cost, subsurface risk, and limited policy attention. That picture is now changing as next‑generation geothermal developers raise larger rounds, sign serious offtake agreements, and move projects from concept to execution.   At the same time, global demand for firm, low‑carbon power is rising faster than conventional geothermal can supply. Thermal plants are retiring, grids need 24/7 clean electricity, and policymakers are discovering that weather‑dependent renewables cannot carry the entire load alone. EGS is emerging as one of the few technologies capable of delivering baseload clean power using a resource available almost everywhere: deep, hot rock. Current EGS Market Size – Small but Strategic In absolute terms, the EGS market is s...

Iceland Drilling, Pertamina Strengthen Geothermal Super Hot Rock Collaboration

Iceland Drilling and Pertamina Drilling Strengthen Geothermal Collaboration: A New Platform for Super Hot Rock Development The global geothermal industry is entering a period in which drilling capability, resource knowledge and international collaboration are becoming increasingly important. As countries look for reliable, low-carbon sources of electricity and heat, geothermal energy is moving beyond conventional developments toward more technically challenging resources, including deeper reservoirs and Super Hot Rock (SHR). A new collaboration between Iceland Drilling Company Ltd and Pertamina Drilling Services Indonesia (PDSI) highlights this transition. In August 2026, Iceland Drilling and Pertamina Drilling Services Indonesia officially signed a Memorandum of Understanding (MoU) aimed at strengthening cooperation in geothermal drilling services. The agreement brings together two organisations from countries with exceptionally strong geothermal credentials: Iceland, with decade...

SECI Invites Geothermal Agencies for Resource Assessment and Power Development in Andaman & Nicobar Islands

SECI’s Geothermal EOI for Andaman & Nicobar Islands: What It Means for India’s Next Frontier in Clean Power The Solar Energy Corporation of India’s EOI for geothermal resource assessment and development in the Andaman & Nicobar Islands is a notable signal that India is widening its renewable-energy playbook beyond solar and wind. For developers, consultants, and investors, this tender is less about a single procurement and more about a strategic entry point into one of India’s most technically intriguing clean-energy frontiers. Why This EOI Matters SECI has published Tender ID SECI000268 under reference SECI/C&P/EOI/17/0003/26-27 for the “Identification and Capability Assessment of Agencies for Geothermal Resource Assessment, Exploration, Development, and Utilization of Geothermal Power Plant in UT of A&N Islands.” The document indicates that the initiative is meant to identify agencies with capability across geothermal resource assessment, exploration, development, and...

Plum IV and CTR’s Geothermal Critical Minerals Deal Takes Shape

Plum Acquisition Corp. IV and  Controlled Thermal Resources Outline a Large-Scale Geothermal and Critical Minerals Platform Plum Acquisition Corp. IV (“Plum IV”) and Controlled Thermal Resources Holdings Inc. (“CTR”) are moving toward a proposed business combination that would create a public company focused on one of the most ambitious geothermal and critical minerals developments in the United States. The combined entity is expected to trade on Nasdaq under the pro forma ticker CTRH, reflecting a platform built around clean baseload power, lithium recovery, and broader critical minerals production. The investor presentation dated August 2026 frames the transaction around CTR’s Hell’s Kitchen project in Imperial County, California, which is presented as a strategically positioned resource opportunity with energy, minerals, infrastructure, and permitting advantages.   At the center of the presentation is a clear message: this is not just a power project, and it is not j...

AFK Geothermie launches €65M dublette drilling to heat 1,200 homes

AFK Geothermie launches second dublette drilling in Aschheim , pathway to 1,200 geothermal heat connections Summary AFK Geothermie has begun preparing the drill site for a second deep geothermal dublette near Aschheim. Drilling is scheduled to start in November at depths up to 2,600 meters. The project aims to supply up to 1,200 residential connections in Aschheim, Feldkirchen and Kirchheim with district heating from January 2028, expanding an established field first tapped in 2008. Total investment is around €65 million, combining public grants, municipal contributions, company equity and long-term loans. Why this matters now The AFK project is a practical example of how municipal-scale geothermal systems move from demonstration to scale-up. As European policymakers push for decarbonized heating, replicable, well-financed geothermal projects that integrate with existing district heating networks are becoming critical. The Aschheim dublette highlights common technical, financial and ...

Geothermal heat pumps for universities: campus decarbonization, industrial heat pumps, and state grant funding

Massachusetts’ $23M Push: How Geothermal, Industrial Heat Pumps and Efficiency Grants Can Transform Campus Decarbonization Image: MIT, Cambridge  Massachusetts’ recent award of approximately $23 million in decarbonization implementation grants to public universities and state facilities is more than a set of individual projects — it’s a practical blueprint for how public-sector institutions can accelerate fossil-fuel retirement, reduce operating costs, and scale up low-carbon heating technologies. The grant round, made through the Department of Energy Resources’ Leading by Example (LBE) Decarbonization Implementation Grant (DIG) program, funds a range of measures from campus-scale geothermal systems to industrial heat pumps, air-source heat pumps, building envelope upgrades, and rooftop solar. Together the projects demonstrate how targeted public investments can unlock larger capital programs, yield sizeable greenhouse gas (GHG) reductions, and create replicable models for universi...

If You Had $1 Billion for Geothermal, Where Should You Invest?

If You Had $1 Billion for Geothermal in 2026, Where Wouldn’t You Invest? Image: A thematic image of a drilling rig on a geothermal, well pad Geothermal is becoming one of the most interesting corners of clean energy, but that does not mean every market deserves your capital. In 2026, the smartest geothermal investors are not asking where the hottest rocks are, they are asking where geology, contracts, policy, and execution line up well enough to justify real money. The real investment test If you had $1 billion to deploy in geothermal, you would not start with hype. You would start with bankability, because geothermal is a business of drilled wells, long timelines, heavy upfront costs, and a very unforgiving path from theory to cash flow. A project can look excellent on a resource map and still underperform badly if permitting drags, community consent is weak, tariffs are mispriced, or the grid cannot absorb the power. That is why this article focuses on where you would not put capita...

Deep Geothermal Drilling Preparation for Renewable District Heating

Deep Drilling Preparation for Geothermal Energy: The Erdwärme Breisgau Project The Erdwärme Breisgau geothermal project has received approval for its next phase, allowing Badenova and Herrenknecht to begin preparing a deep-drilling site near Hartheim in Baden-Württemberg, Germany. The partners plan to invest approximately €60 million to explore a geothermal reservoir located around 3,200 metres underground and develop a heating plant for regional district heating.  Why Deep Drilling Matters for Geothermal Heating Deep geothermal energy can provide a stable, renewable source of heat for district-heating networks. Unlike solar and wind power, which depend on weather conditions, geothermal heating can operate continuously when the underground reservoir and surface infrastructure are technically and economically viable. The Erdwärme Breisgau project is designed to investigate a hot-water reservoir beneath the Hartheim area. The plan involves drilling two directional wells: one producti...

Geothermal Drilling Cost Per Well: U.S. and Global Benchmarks by Country

Geothermal Drilling Cost Per Well: U.S. and Global Benchmarks by Country Geothermal drilling cost per well varies widely because no two projects face the same depth, geology, reservoir temperature, or drilling risk. In the United States and other major geothermal markets, costs can range from modest amounts for shallow residential boreholes to several million dollars for deep power-generation wells. A single “average” price is therefore misleading. The most useful way to understand geothermal drilling cost is to look at project type, depth, and country together, then compare those figures against the conditions that drive them. What A Geothermal Well Includes A geothermal well is more than a hole in the ground. It is a highly engineered underground asset that must be drilled, cased, cemented, tested, and often completed under demanding temperature and pressure conditions. For residential systems, the well or borehole is part of a ground-source heat pump loop field. For power projects, ...

Quaise Energy Raises $180 Million Series B to Advance Superhot Geothermal Power Plant

Quaise Energy Raises $180 Million as Superhot Geothermal Moves Closer to Commercial Reality Quaise Energy has taken a major step toward commercializing superhot geothermal power with the final close of its Series B financing, bringing in $180 million in equity capital and lifting total funding to $280 million. The round includes a $35 million investment from Nabors Industries and a strategic framework agreement that strengthens the companies’ collaboration around drilling operations, technology integration, and commercial development. The announcement matters because it is not just another clean-energy funding headline. It is a signal that superhot geothermal is starting to attract the kind of capital, industrial partnerships, and technical confidence that are usually needed before a frontier energy technology can move from laboratory promise to real-world deployment. A Big Capital Milestone The final close of the Series B gives Quaise a stronger financial base to advance Project Obs...