Geothermal Exploration in Taranaki and Waikato: Unlocking New Energy Opportunities in New Zealand New Zealand is expanding its geothermal ambitions beyond the country’s established development zones. Two Māori-led exploration projects in Taranaki and South Waikato have received a combined NZ$5.95 million in government grants to investigate previously underexplored geothermal resources and assess their potential to support regional growth, energy resilience, employment, and decarbonisation.  The initiatives reflect a broader shift in geothermal development. While New Zealand’s geothermal industry has traditionally focused on high-temperature resources suitable for electricity generation, the new projects will also examine lower-temperature heat that could serve industrial, agricultural, commercial, and community applications. Government Funding for Two Exploration Projects The New Zealand Government has allocated NZ$3 million from the Regional Infrastructure Fund to the Taranaki Ge...

Eavor Demobilizes Rigs in Geretsried: What It Means for Closed-Loop Geothermal Investors, Heat Markets, and Project Risk

Eavor Demobilizes Rigs from Geretsried: What It Really Means for Closed-Loop Geothermal

For three years, two drilling rigs on a farm estate near Geretsried, a Bavarian town about 40 km south of Munich, stood as the symbol of the world's most ambitious closed-loop geothermal experiment. Now in October 2026, 

Eavor Technologies, the Calgary-based developer of the Eavor-Loop, has told the town and its heating utility that both rigs would leave the site . The company said keeping idle rigs and specialist services on site was costly, and that releasing them would help put the project in the strongest position to continue with Loop 2 once its commercial structure is reworked .

On the surface, this is a logistics decision. Underneath, it is one of the clearest signals yet about where first-of-a-kind geothermal technology stands, and how hard it is to turn a technical proof into a bankable business. This article explains exactly what happened, what the move means and what it does not mean, and what investors, utilities and the wider geothermal sector should watch next.

What Eavor Actually Announced

The facts are narrower than some headlines suggest.

Eavor is releasing two drilling rigs from Geretsried. It is not shutting the plant down. The existing loop keeps operating, and Eavor says it is refocusing the project's commercial structure on selling heat . The company says Geretsried remains a priority project and that it is negotiating a firm heat offtake agreement .

What has changed is timing. Construction of the second loop, the second of four planned, is postponed indefinitely, and no restart date has been set (BR24). Eavor had originally hoped to begin Loop 2 drilling in March 2026, but the evaluation phase after Loop 1 took longer than planned (ZfK).

So the short answer to "what does this mean?" is this: Eavor has stopped paying for drilling capacity it cannot yet use, because the money, the partners and the heat contract needed to drill Loop 2 are not yet in place.

Why the Rigs Were Still There

To understand the rig demobilization, you need to know what the rigs were waiting for.

The Geretsried design called for four Eavor-Loops, each with 12 lateral pairs about 6 km long, for roughly 72 km of reservoir exposure. The surface plant was sized for 8.2 MW of electricity and 64 MW of heat (Eavor). Two rigs supplied by KCA Deutag drilled Loop 1 between July 2023 and October 2025, which works out to about 27 months against an original plan of 107 drilling days (Autonocion).

The rigs were kept on site because the plan was to move straight into Loop 2. In May 2026, Eavor CEO Mark Fitzgerald said the company was working to secure the best path forward quickly, partly because the two rigs that drilled the initial wells were still standing at Geretsried . Five months later, with no additional financing or firm offtake publicly confirmed, the cost of standby won out.

Eavor has not disclosed what the rigs cost per day on standby . Any specific daily figure you see quoted online should be treated as an estimate, not a reported number.

What Went Wrong Underground


1. Poor cementing of the motherbores
Efficient Eavor-Loop construction depends on two rigs drilling in parallel, with each lateral pair drilled from both sides at once and intersected deep underground. After the second lateral pair, Eavor measured fluid flowing between the two rigs. The root cause was poor cement on both cased vertical "motherbores," which created a channel behind the casing linking the lateral pairs (Eavor).

That forced Eavor to drill with one rig at a time, which the company says effectively doubled time and cost (Eavor). It also allowed cuttings-laden drilling fluid to flow back into previously drilled laterals.

2. Debris in the laterals
Five of the six lateral pairs ended up with mud and cuttings inside them. Eavor flushed three of those and confirmed the result with production logging, but chose not to clean the first two pairs because the cost and time were prohibitive (Eavor). Because of the impact on cost and schedule, Eavor stopped Loop 1 at six lateral pairs instead of the 12 in the original design. Four pairs are now operating as expected.

3. Drilling fluid and drilling dynamics

The original mud system, based on successful hydrothermal wells in southern Germany, was poorly suited to some of the carbonate formations, creating hole-cleaning problems and stuck-pipe risk. Hard rock, long laterals and high friction also caused shock, vibration and tool damage (Eavor). SLB's head of drilling engineering, Blaine Dow, also noted that the rigs had barely worked in the previous four years and that the crews were mostly new .

The Output Gap in Plain Numbers

This is where the Geretsried story gets most attention, and most confusion. Here are the reported figures side by side.

Two points matter for a fair reading.

First, the comparison of "2 MW versus 8.2 MW" is not like-for-like. The 8.2 MWe figure is for four complete loops with 48 lateral pairs as per the original design. Today there is one partial loop with four working pairs. Eavor says that configuration should deliver roughly a third of one full loop's heat (Eavor), which is about one-twelfth of the full project (Autonocion). Eavor argues that heat output per pair matches its pre-drill predictions.

Second, the electricity numbers are still weak. The Turboden ORC plant was sized for the full project, so it is badly oversized for one partial loop. Fitzgerald said plant efficiency was only about 2% with so few loops contributing, and could rise to 14% if more loops came online. When the plant uses roughly as much power as it makes, net grid supply is close to zero most of the time.

In short, the subsurface heat model appears to be working. The construction speed, the capital cost and the amount of reservoir actually built are what fell short.

The Money Behind the Move

Rigs are withdrawn when capital gets tight, and Geretsried's capital story is the real driver here.
The project was backed by a €91.6 million grant from the EU Innovation Fund and a European Investment Bank loan of up to €45 million (BR24). According to Eavor, the original budget for the overall project, comprising four Eavor Loops, was approximately €350 million. Around two-thirds of this amount has been made available to date. This covers not only the completion of Loop 1, but also the entire infrastructure and the above-ground facilities for the overall power plant concept.

The project was awarded €91.6 million in funding from the EU Innovation Fund. Payments are made in instalments linked to the achievement of contractually agreed milestones. The most recent payment was made following the successful commissioning of the first Loop. Further payments will be made as subsequent project milestones are achieved. The final funding instalment will be paid following successful completion of the overall project, during the subsequent ten-year monitoring period. This is subject to annual verification of the GHG avoidance agreed in the Grant Agreement. A delay in full commissioning does not affect the total funding amount. It only requires an adjustment to the project timeline and payment schedule under the EU Innovation Fund.

From Operator to Technology Provider
The rig release is the physical result of a strategic shift that started in spring 2026.

In May, Eavor cut its headcount from 147 to 80 and said it would step away from being the primary developer for future projects. "We see ourselves as a technology provider," Fitzgerald said, "as we believe that other parties may be more capable of the operational side of things" . 

He also said: "We believe that we have proven the concept. We now have to prove commerciality."

This needs a precise reading. Eavor is not giving up its stake in Geretsried. Fitzgerald later stressed, "We are not stepping away from Geretsried. Let me be clear on that," and said the company's ownership position and commitment to finishing the project remain unchanged (ThinkGeoEnergy). What is changing is who carries the drilling and execution risk. Eavor wants partners with deep multilateral drilling experience to build future loops, while it focuses on engineering, technology, and its proprietary tools.

Those tools are real assets. The Eavor-Link™ Active Magnetic Ranging (AMR) system puts ranging into the drilling assembly so wells can be steered together while drilling. Using it, Eavor hit first-attempt intersections on all six lateral pairs at about 8 km measured depth (Eavor). Its Rock-Pipe™ sealant cut near-wellbore permeability by more than an order of magnitude, and leak-off has stayed between 0.5% and 2% of circulating fluid (Eavor).

What It Means for Geretsried

For the town, the impact is immediate. Isar-Loisach-Naturwärme (ILN), the district heating subsidiary of Stadtwerke Geretsried, called the delay "a severe setback for Geretsried" and said there is currently no reliable commitment from 

Eavor to build the second loop .

Loop 2 was the precondition for district heating. The town has been waiting to build its heat network until that loop is finished (ZfK). ILN signed a heat supply agreement with Eavor in 2024 for 81,200 MWh per year , and it now says it will reassess how to secure heat, including continued work with Eavor and alternative or supplementary sources. The city has also criticised Eavor's "sluggish communication," saying it was informed at very short notice .

That matters beyond Bavaria. In 2023, then-Chancellor Olaf Scholz called the project a "technical masterpiece" during a site visit (BR24). When a showcase project stalls, the political and reputational cost lands on the whole next-generation geothermal sector, not just one company.

What It Means for Closed-Loop Geothermal

It would be wrong to read the rig withdrawal as proof that closed-loop geothermal does not work. It would be just as wrong to read it as a minor pause.

What Geretsried proved

Long laterals can be drilled and intersected reliably at about 8 km measured depth, with first-attempt intersections on all six pairs (Eavor).

Heat output per lateral pair matched Eavor's predictions, at more than 2 MWth per operating pair (Eavor).

The learning curve is steep and real. Average drilling time fell from 54.5 days per pair for the first four pairs to 16.5 days for the last two (Autonocion), and Eavor expects future pairs to take about three weeks each (Eavor).

What Geretsried has not yet proved
That a full Eavor-Loop can be built on budget and on schedule.

That electricity from closed-loop systems in average-gradient rock can compete without much deeper, hotter wells. Eavor itself says depth is the key lever, pointing to 20 MWe at 15 km depth in a 30°C/km gradient versus 2 MWe at Geretsried, and admits current drilling technology hits limits below about 9 km true vertical depth (Eavor).

That a third-party driller will accept the construction risk on commercial terms.

The most realistic near-term market is heat, not power. Eavor says its economics are already competitive for European district heating, based on the last two lateral pairs drilled . That fits with its decision to refocus Geretsried on heat sales.

It is important to note that the existing Loop already provides a continuous thermal output of 8 MW. This represents a significant source of clean and reliable heat that can be utilized once a suitable heat offtake opportunity has been secured.

What to Watch Next

For investors, utilities and policymakers, these are the five signals that will decide whether the rigs come back:

A named drilling or operating partner. Eavor has said it is in talks with candidates but has not named any .

A firm heat offtake agreement with ILN or other buyers, replacing the 2024 contract terms that ILN says have shifted.

New project financing for Loop 2, and clarity on the status of the EU Innovation Fund grant.
ILN shareholders' decision on whether to continue with Eavor, turn to other heat sources, or both (Autonocion).
Eavor-Loop 2.0 projects in crystalline basement rock, which Eavor says it and its partners are actively developing for heat and power markets (Eavor).

The Bottom Line

The rigs may be moving but Eavor is not walking away from Geretsried, nor is it admitting the physics failed. It is admitting something more ordinary and, for the industry, more important: a first-of-a-kind project ran out of time and needs to preserve capital to reach its designed scale, and the next phase cannot start until someone else shares the risk.

Loop 1 delivered what Eavor calls a technical proof of concept: precise deep intersections, predictable heat per lateral pair and a fast-improving drilling curve. It has not yet delivered r the 8.2 MW plant the town, the EU, and investors were promised, and the district heating that Geretsried planned around is now on hold.

The rigs leaving Bavaria mark the end of Eavor's first chapter as a builder-operator. Whether Geretsried becomes the template for closed-loop geothermal or a costly lesson will depend on what happens at the negotiating table, not on the drilling floor. 

Source: Email Correspondence From Eavor Technologies 

Comments

Popular posts from this blog

"GE Hitachi Nuclear Energy, OPG, SNC-Lavalin and Aecon Sign Historic Contract for Deployment of Groundbreaking Small Modular Reactor at Darlington Nuclear Project Site"

image source:(unsplash.com,Jakob Madsen) GE Hitachi Nuclear Energy (GEH), in partnership with Ontario Power Generation (OPG), SNC-Lavalinand Aecon, has signed a contract for the deployment of a BWRX-300 small modular reactor (SMR) at OPG’s Darlington New Nuclear Project site, marking the first commercial contract for a grid-scale SMR in North America. This groundbreaking agreement, through which GEH will provide the reactor design, encompasses a comprehensive range of project activities, including design, engineering licensing support, construction, testing, training and commissioning. Jay Wileman, President and CEO of GEH, stated, "This contract is an important milestone and solidifies our position as the leading SMR technology provider. We aim to deliver the first SMR in North America and, in doing so, lead the start of a new era of nuclear power that will provide zero-emission energy generation, energy security and energy reliability around the globe. We can’t express our appre...

KenGen Risks Losing Olkaria Geothermal Wells Over Licence Error

KenGen Risks Losing Olkaria Wells Over 18-Year Licence Blunder Kenya Electricity Generating Company (KenGen) faces a serious legal and operational risk at Olkaria after an error in the coordinates of its geothermal licence left part of the company’s wells, steam infrastructure and other assets outside its legally recognised area. The licensing mistake, made nearly two decades ago, remains unresolved despite the Ministry of Energy and Petroleum acknowledging the problem in 2017.  The dispute has raised questions about the security of KenGen’s investments, the government’s management of geothermal resources and the potential consequences for Kenya’s electricity supply. Olkaria is the country’s most important geothermal centre and accounts for the overwhelming majority of Kenya’s installed geothermal generation capacity.  Licence Error Exposes Strategic Assets The problem dates back to September 19, 2008, when the Ministry of Energy and Petroleum issued KenGen a licence covering ...

Djibouti Pays KenGen: $1M Offer on a Five-Year Geothermal Drilling Debt

Djibouti Pays KenGen: A $1 Million Offer on a Five-Year-Old Geothermal Drilling Debt Djibouti has finally moved to pay part of what it owes Kenya Electricity Generating Company (KenGen) for drilling work done near Lake Assal. The amount is small next to KenGen's balance sheet. What it says about selling geothermal drilling services across Africa matters a lot more. KenGen's latest annual report says Djibouti's state geothermal agency, the Office Djiboutien de Développement de l'Énergie Géothermique (ODDEG), has offered a first instalment of about $1 million (Sh129 million) against outstanding invoices of $2.13 million (Sh276.03 million), according to Business Daily. "ODDEG has acknowledged the debt and has proposed an initial payment of $1 million as the first instalment towards settlement," KenGen said in the report. KenGen is Kenya's largest power producer, with about 54% of the market. The Kenyan government owns 70% of the company and the public holds t...

Lithium Harvest Plans Alberta Geothermal Power and Lithium Project

Lithium Harvest’s Alberta Geothermal Project Could Combine Renewable Power and Domestic Lithium Production Lithium Harvest Holding A/S has signed a letter of intent with an unnamed geothermal development partner to establish a joint venture for an integrated geothermal power and lithium production facility in Alberta, Canada. At full nameplate capacity, the proposed project is expected to produce approximately 28,500 tonnes of lithium carbonate annually while generating 0.67 TWh of renewable electricity each year. The development would use a single geothermal resource to supply both baseload power and lithium-bearing brine for direct lithium extraction and refining.  A Dual-Output Geothermal Development The proposed Alberta facility reflects a growing effort to extract more value from geothermal resources than electricity generation alone. Traditional geothermal power projects produce electricity by bringing hot underground fluids to the surface. Depending on resource temperature a...

Corva and Oliasoft Connect Well Design With Real-Time Drilling

Corva and Oliasoft Build a Continuous Learning Loop for Smarter Well Construction Introduction Corva AI and Oliasoft have announced a strategic collaboration designed to connect well engineering, real-time drilling operations and post-well analysis through a bidirectional digital workflow. The integration links Oliasoft WellDesign with Corva’s Real-Time AI platform, creating a continuous information loop in which engineering plans guide field execution and drilling results improve future well designs.  The partnership addresses one of the persistent weaknesses in modern well construction: the separation between planning software and operational systems. Although operators generate large volumes of engineering and drilling data, those datasets often remain fragmented across departments, applications and reporting processes. The result is slower decision-making, repeated manual work and limited transfer of lessons from one well to the next. By connecting design assumptions with liv...

BLM Nevada Geothermal Lease Auction Boosts Renewable Energy Investment amid Solar Land Conflict

BLM’s Nevada Geothermal Lease Auction Signals Rising Competition for Federal Energy Land The Bureau of Land Management’s latest geothermal lease sale in Nevada attracted nearly $4.83 million in total receipts, highlighting growing investor interest in geothermal resources as electricity demand rises . The auction also exposed an increasingly important land-use conflict: several geothermal parcels overlap with proposed utility-scale solar projects, including NextEra Energy’s 1,000-megawatt Sawtooth Energy Center. The October 20, 2026, sale offered 83 parcels covering approximately 265,155 acres across 10 Nevada counties. Bidders placed offers on 60 parcels covering 186,641 acres, while 23 parcels received no bids. The results provide a new measure of competition for federal geothermal acreage in one of the United States’ most important geothermal states. Auction Results The Nevada auction attracted 32 registered bidders, of which 18 submitted at least one bid. Across the sale, bidders s...

Endurance Energy Tests World's First Subsea Geothermal Well at Axial Seamount

Endurance Energy Tests the World's First Subsea Geothermal Well: What the Axial Seamount Demonstration Really Proved What if geothermal energy did not need a power plant on land? What if electricity could be produced directly from the Earth's heat beneath the ocean, with generators sitting on the seafloor and sending power to coastal grids? On October 19, 2026, Seattle-based startup Endurance Energy announced a major step toward that idea. The company said it had drilled and completed the world's first subsea geothermal well and placed a 3-ton test power plant nearly a mile beneath the Pacific. It also reported net-positive electricity from heat at an active underwater volcano, according to its announcement on PR Newswire. The headline numbers are modest. The Adélie prototype produced more electricity than it used for about 8.7 seconds. During that time it delivered a median net output of about 2 kilowatts and a peak of 16.5 kilowatts. One detail matters more than any other...

Geiselbullach Geothermal Project Confirms 10 MW District Heating Capacity

Geothermal milestone at Geiselbullach: 10 MW of heat confirmed after successful second deep well test On 15 August 2026 the Geiselbullach geothermal project reached a pivotal technical milestone: performance testing of the second deep production well completed successfully, delivering a sustained flow of 90 liters per second of thermal water at 79–80 °C. These measured parameters translate into roughly 10 MW of usable thermal power for district heating, enough to replace a portion of heat currently supplied by the municipal waste-to-energy plant (AHKW) and to create headroom for expanding the regional district heating network. The result confirms the project’s technical assumptions and moves the scheme into system-integration and commissioning activities ahead of planned commercial deliveries for the 2027 heating season. This article explains the test results and their significance, outlines the technical and operational consequences, and places the Geiselbullach development in the bro...

Menengai Geothermal Project Delays Expose Kenya’s Broken Steam Supply Model

Menengai’s Broken Promise: How Kenya’s Geothermal Model Lost the Steam Thematic image of the Olkaria Geothermal Field  Kenya’s Menengai geothermal project was sold as a model of modern public-private partnership. The state would carry the difficult and expensive burden of geothermal exploration and drilling. Private power producers would then build, own and operate power plants. Geothermal Development Company would supply the steam; the independent power producers would convert it into electricity; Kenya Power would buy the output. On paper, the arrangement was elegant. In practice, Menengai has exposed a far more uncomfortable reality: Kenya’s public steam-supply model is not delivering the certainty it promised. Menengai Phase I was designed to produce 105 megawatts from three 35 MW plants. GDC’s own project page says the three plants were awarded to Globeleq Menengai Geothermal, Sosian Menengai Geothermal Power and OrPower Twenty Two under a build-own-operate structure. Yet the ...