Geothermal Exploration in Taranaki and Waikato: Unlocking New Energy Opportunities in New Zealand New Zealand is expanding its geothermal ambitions beyond the country’s established development zones. Two Māori-led exploration projects in Taranaki and South Waikato have received a combined NZ$5.95 million in government grants to investigate previously underexplored geothermal resources and assess their potential to support regional growth, energy resilience, employment, and decarbonisation.  The initiatives reflect a broader shift in geothermal development. While New Zealand’s geothermal industry has traditionally focused on high-temperature resources suitable for electricity generation, the new projects will also examine lower-temperature heat that could serve industrial, agricultural, commercial, and community applications. Government Funding for Two Exploration Projects The New Zealand Government has allocated NZ$3 million from the Regional Infrastructure Fund to the Taranaki Ge...

Grenada Geothermal Project Advances With Slimhole Wells Procurement.

Grenada’s Geothermal Slimhole Procurement Signals Project Momentum

Grenada has moved another step forward in its geothermal drilling program with a new invitation to bid for civil infrastructure and water supply equipment for two geothermal slimhole wells, a procurement package that points to concrete field preparation rather than just planning on paper . The notice breaks the work into three lots and covers access roads, drill pad civil works, water supply infrastructure, and power equipment needed to support drilling operations .

Project Context

The procurement is being issued by Grenada’s Ministry of Climate Resilience, the Environment and Renewable Energy through its Project Management Unit, while the Ministry of Infrastructure serves as the executing agency . The works are tied to the Government of Grenada’s geothermal drilling project and are being financed in part by the Caribbean Development Bank, according to the notice [1]. That funding link matters because it shows the project is advancing within a formal multilateral financing structure, which usually brings tighter procurement rules and clearer delivery milestones.

For geothermal development, civil works are not a side issue; they are one of the enabling layers that determine whether drilling can proceed safely, efficiently, and on schedule. Access roads, water intake systems, pipelines, and pad preparation all shape rig mobility, water availability, and site readiness before a single well is drilled. In that sense, this tender is a practical marker of project maturity rather than a generic administrative notice .

What The Tender Covers

The invitation to bid is divided into three lots, giving contractors the option to bid on separate components rather than the full package as one bundle . Lot 1 covers access roads, water supply infrastructure, and drill pad civil works for Site C, while Lot 2 covers the same scope for Site F . Lot 3 covers diesel generators and submersible electric pumps, which suggests the project needs independent power and pumping capability to support water handling and site operations .

The works described are broad enough to include construction of water intake infrastructure, water supply pipelines, drill pad civil infrastructure, access road improvements, associated electrical and mechanical systems, testing and commissioning, and related ancillary works [1]. That scope indicates the tender is not limited to a single construction task but to an integrated package of site-enabling infrastructure. For geothermal developers, that kind of integration is important because drilling logistics often fail when civil, water, and power systems are not coordinated well enough .

Why Slimhole Wells Matter

Slimhole wells are commonly used as a lower-cost way to test geothermal potential before committing to larger production wells, which makes them especially useful in frontier or early-stage geothermal markets. In practical terms, they help developers confirm reservoir temperatures, permeability, and fluid characteristics while controlling up-front risk. Grenada’s decision to procure support works for two slimhole wells suggests the country is still building the evidence base needed to advance toward a commercial geothermal field.

This is particularly significant for an island state where energy security, fuel import exposure, and electricity costs are closely watched policy issues. Geothermal could offer firm renewable capacity if drilling confirms a viable resource, but the project must clear each technical and logistical step first. Civil infrastructure procurement is one of those steps because drilling campaigns require reliable water, manageable site access, and stable operating conditions .

Financing And Governance

The notice states that the Government of Grenada has received financing from the Caribbean Development Bank and will use part of the proceeds for eligible payments under the contract [1]. It also notes that payments by the CDB will occur only at the request of the Government of Grenada and subject to approval by the bank, which is standard language in development-financed procurement . That structure helps ensure compliance with the loan agreement and strengthens oversight over how project funds are used .

The notice also includes the standard restriction that funds cannot be used for payments or imports prohibited under United Nations Security Council decisions, a clause commonly found in multilaterally financed contracts.While that language is procedural, it signals that the project is being managed under formal international financing discipline rather than ad hoc public spending. For contractors, that usually means clearer documentation requirements, stricter eligibility rules, and a more structured evaluation process .

Market Implications

For the geothermal supply chain, this tender is relevant beyond Grenada because it shows how small-island geothermal projects move from policy ambition into procurement reality. Civil works packages like these often create opportunities for road builders, civil contractors, electrical-mechanical suppliers, and pump or generator vendors. In emerging geothermal markets, these early packages can be just as important as drilling contracts because they establish the physical backbone that drilling depends on .

The split into multiple lots may also broaden participation by allowing firms with specific capabilities to bid on narrower scopes. That can help a project attract more competition and reduce dependence on a single all-in contractor, especially where local capacity is being developed. For regional contractors in the Caribbean, this kind of procurement can be a gateway into geothermal infrastructure work if they have relevant civil and mechanical experience .

What Bidders Need To Notice

Bidders should pay close attention to the lot structure, because each lot appears to cover a distinct geographic or equipment package. Site C and Site F may present different access or logistical conditions, so pricing and construction methods may vary materially between them. Lot 3 is also separate from the civil packages, which may appeal to suppliers of generators, pumps, and related electrical systems rather than general contractors.

The notice says the Ministry of Climate Resilience, the Environment and Renewable Energy Project Management Unit is inviting electronic bids from eligible and qualified bidders [1]. That means the procurement is likely being run through a formal online submission process, so compliance with bid format, eligibility documentation, and deadline requirements will be essential. In development-financed tenders, even technically strong bids can be disqualified if they miss submission rules or omit required forms .

Grenada’s Energy Strategy

Grenada has been positioning geothermal as part of its broader renewable energy transition, and this procurement suggests the country is continuing to push the project forward in measurable stages. Slimhole drilling is often an early proof point in geothermal development, especially in volcanic island settings where resource confirmation is critical before scaling up. If successful, the project could support long-term energy diversification and reduce exposure to imported fossil fuels.

The tender also reflects the practical sequencing of geothermal development: first secure financing, then prepare sites, then drill, then evaluate the resource, and only later consider expansion. That sequencing can look slow from the outside, but it is the normal discipline of geothermal project development. In Grenada’s case, the current tender shows that the project has moved into a more tangible phase where infrastructure on the ground is being organized for drilling activity .

 What Happens Next

The most immediate next step is the bid process itself, which will determine which contractors are selected for each lot. After that, the chosen firms would typically move into mobilization, site preparation, and the installation or upgrading of access roads, water systems, pads, and support equipment. Once that work is complete, the project will be better positioned for drilling operations at the slimhole sites .
The CDB procurement notice lists the opportunity as a works contract for Grenada, with a deadline of Nov. 6, 2026 at 12:00 PM . 

That gives interested contractors a defined window to prepare compliant submissions and price the work according to the site conditions and technical requirements. For observers of the geothermal sector, it is another sign that Grenada’s project is progressing through the necessary stages toward subsurface testing .





Comments

Popular posts from this blog

"GE Hitachi Nuclear Energy, OPG, SNC-Lavalin and Aecon Sign Historic Contract for Deployment of Groundbreaking Small Modular Reactor at Darlington Nuclear Project Site"

image source:(unsplash.com,Jakob Madsen) GE Hitachi Nuclear Energy (GEH), in partnership with Ontario Power Generation (OPG), SNC-Lavalinand Aecon, has signed a contract for the deployment of a BWRX-300 small modular reactor (SMR) at OPG’s Darlington New Nuclear Project site, marking the first commercial contract for a grid-scale SMR in North America. This groundbreaking agreement, through which GEH will provide the reactor design, encompasses a comprehensive range of project activities, including design, engineering licensing support, construction, testing, training and commissioning. Jay Wileman, President and CEO of GEH, stated, "This contract is an important milestone and solidifies our position as the leading SMR technology provider. We aim to deliver the first SMR in North America and, in doing so, lead the start of a new era of nuclear power that will provide zero-emission energy generation, energy security and energy reliability around the globe. We can’t express our appre...

Eavor Demobilizes Rigs in Geretsried: What It Means for Closed-Loop Geothermal Investors, Heat Markets, and Project Risk

Eavor Demobilizes Rigs from Geretsried: What It Really Means for Closed-Loop Geothermal For three years, two drilling rigs on a farm estate near Geretsried, a Bavarian town about 40 km south of Munich, stood as the symbol of the world's most ambitious closed-loop geothermal experiment. Now in October 2026,  Eavor Technologies, the Calgary-based developer of the Eavor-Loop, has told the town and its heating utility that both rigs would leave the site . The company said keeping idle rigs and specialist services on site was costly, and that releasing them would help put the project in the strongest position to continue with Loop 2 once its commercial structure is reworked . On the surface, this is a logistics decision. Underneath, it is one of the clearest signals yet about where first-of-a-kind geothermal technology stands, and how hard it is to turn a technical proof into a bankable business. This article explains exactly what happened, what the move means and what it does not mean...

KenGen Risks Losing Olkaria Geothermal Wells Over Licence Error

KenGen Risks Losing Olkaria Wells Over 18-Year Licence Blunder Kenya Electricity Generating Company (KenGen) faces a serious legal and operational risk at Olkaria after an error in the coordinates of its geothermal licence left part of the company’s wells, steam infrastructure and other assets outside its legally recognised area. The licensing mistake, made nearly two decades ago, remains unresolved despite the Ministry of Energy and Petroleum acknowledging the problem in 2017.  The dispute has raised questions about the security of KenGen’s investments, the government’s management of geothermal resources and the potential consequences for Kenya’s electricity supply. Olkaria is the country’s most important geothermal centre and accounts for the overwhelming majority of Kenya’s installed geothermal generation capacity.  Licence Error Exposes Strategic Assets The problem dates back to September 19, 2008, when the Ministry of Energy and Petroleum issued KenGen a licence covering ...

Djibouti Pays KenGen: $1M Offer on a Five-Year Geothermal Drilling Debt

Djibouti Pays KenGen: A $1 Million Offer on a Five-Year-Old Geothermal Drilling Debt Djibouti has finally moved to pay part of what it owes Kenya Electricity Generating Company (KenGen) for drilling work done near Lake Assal. The amount is small next to KenGen's balance sheet. What it says about selling geothermal drilling services across Africa matters a lot more. KenGen's latest annual report says Djibouti's state geothermal agency, the Office Djiboutien de Développement de l'Énergie Géothermique (ODDEG), has offered a first instalment of about $1 million (Sh129 million) against outstanding invoices of $2.13 million (Sh276.03 million), according to Business Daily. "ODDEG has acknowledged the debt and has proposed an initial payment of $1 million as the first instalment towards settlement," KenGen said in the report. KenGen is Kenya's largest power producer, with about 54% of the market. The Kenyan government owns 70% of the company and the public holds t...

Lithium Harvest Plans Alberta Geothermal Power and Lithium Project

Lithium Harvest’s Alberta Geothermal Project Could Combine Renewable Power and Domestic Lithium Production Lithium Harvest Holding A/S has signed a letter of intent with an unnamed geothermal development partner to establish a joint venture for an integrated geothermal power and lithium production facility in Alberta, Canada. At full nameplate capacity, the proposed project is expected to produce approximately 28,500 tonnes of lithium carbonate annually while generating 0.67 TWh of renewable electricity each year. The development would use a single geothermal resource to supply both baseload power and lithium-bearing brine for direct lithium extraction and refining.  A Dual-Output Geothermal Development The proposed Alberta facility reflects a growing effort to extract more value from geothermal resources than electricity generation alone. Traditional geothermal power projects produce electricity by bringing hot underground fluids to the surface. Depending on resource temperature a...

Corva and Oliasoft Connect Well Design With Real-Time Drilling

Corva and Oliasoft Build a Continuous Learning Loop for Smarter Well Construction Introduction Corva AI and Oliasoft have announced a strategic collaboration designed to connect well engineering, real-time drilling operations and post-well analysis through a bidirectional digital workflow. The integration links Oliasoft WellDesign with Corva’s Real-Time AI platform, creating a continuous information loop in which engineering plans guide field execution and drilling results improve future well designs.  The partnership addresses one of the persistent weaknesses in modern well construction: the separation between planning software and operational systems. Although operators generate large volumes of engineering and drilling data, those datasets often remain fragmented across departments, applications and reporting processes. The result is slower decision-making, repeated manual work and limited transfer of lessons from one well to the next. By connecting design assumptions with liv...

BLM Nevada Geothermal Lease Auction Boosts Renewable Energy Investment amid Solar Land Conflict

BLM’s Nevada Geothermal Lease Auction Signals Rising Competition for Federal Energy Land The Bureau of Land Management’s latest geothermal lease sale in Nevada attracted nearly $4.83 million in total receipts, highlighting growing investor interest in geothermal resources as electricity demand rises . The auction also exposed an increasingly important land-use conflict: several geothermal parcels overlap with proposed utility-scale solar projects, including NextEra Energy’s 1,000-megawatt Sawtooth Energy Center. The October 20, 2026, sale offered 83 parcels covering approximately 265,155 acres across 10 Nevada counties. Bidders placed offers on 60 parcels covering 186,641 acres, while 23 parcels received no bids. The results provide a new measure of competition for federal geothermal acreage in one of the United States’ most important geothermal states. Auction Results The Nevada auction attracted 32 registered bidders, of which 18 submitted at least one bid. Across the sale, bidders s...

Endurance Energy Tests World's First Subsea Geothermal Well at Axial Seamount

Endurance Energy Tests the World's First Subsea Geothermal Well: What the Axial Seamount Demonstration Really Proved What if geothermal energy did not need a power plant on land? What if electricity could be produced directly from the Earth's heat beneath the ocean, with generators sitting on the seafloor and sending power to coastal grids? On October 19, 2026, Seattle-based startup Endurance Energy announced a major step toward that idea. The company said it had drilled and completed the world's first subsea geothermal well and placed a 3-ton test power plant nearly a mile beneath the Pacific. It also reported net-positive electricity from heat at an active underwater volcano, according to its announcement on PR Newswire. The headline numbers are modest. The Adélie prototype produced more electricity than it used for about 8.7 seconds. During that time it delivered a median net output of about 2 kilowatts and a peak of 16.5 kilowatts. One detail matters more than any other...

Geiselbullach Geothermal Project Confirms 10 MW District Heating Capacity

Geothermal milestone at Geiselbullach: 10 MW of heat confirmed after successful second deep well test On 15 August 2026 the Geiselbullach geothermal project reached a pivotal technical milestone: performance testing of the second deep production well completed successfully, delivering a sustained flow of 90 liters per second of thermal water at 79–80 °C. These measured parameters translate into roughly 10 MW of usable thermal power for district heating, enough to replace a portion of heat currently supplied by the municipal waste-to-energy plant (AHKW) and to create headroom for expanding the regional district heating network. The result confirms the project’s technical assumptions and moves the scheme into system-integration and commissioning activities ahead of planned commercial deliveries for the 2027 heating season. This article explains the test results and their significance, outlines the technical and operational consequences, and places the Geiselbullach development in the bro...

Menengai Geothermal Project Delays Expose Kenya’s Broken Steam Supply Model

Menengai’s Broken Promise: How Kenya’s Geothermal Model Lost the Steam Thematic image of the Olkaria Geothermal Field  Kenya’s Menengai geothermal project was sold as a model of modern public-private partnership. The state would carry the difficult and expensive burden of geothermal exploration and drilling. Private power producers would then build, own and operate power plants. Geothermal Development Company would supply the steam; the independent power producers would convert it into electricity; Kenya Power would buy the output. On paper, the arrangement was elegant. In practice, Menengai has exposed a far more uncomfortable reality: Kenya’s public steam-supply model is not delivering the certainty it promised. Menengai Phase I was designed to produce 105 megawatts from three 35 MW plants. GDC’s own project page says the three plants were awarded to Globeleq Menengai Geothermal, Sosian Menengai Geothermal Power and OrPower Twenty Two under a build-own-operate structure. Yet the ...