Geothermal energy presents an engineering paradox: the hotter the underground rock, the greater its potential value,and the harder it becomes to reach with reliable drilling equipment. Mazama Energy’s latest field demonstration addresses that tension directly. By using supercritical carbon dioxide to cool drilling tools, the company reports that it protected sensitive equipment while drilling through exceptionally hot rock and increased drilling speed by 20%. The result points toward a possible route to less expensive wells and access to more productive geothermal resources. Announced on November 16, 2026, the demonstration took place in August at Mazama’s Athena Project at Newberry, Oregon. Its significance lies not in establishing a completed commercial power system, but in addressing an important obstacle between promising underground heat and dependable electricity production. To understand its potential, it is necessary to separate what the company demonstrated from what rema...
Marriott Drilling and Cornish Lithium: A Major Step Toward a Domestic Lithium Future
Cornish Lithium has awarded Marriott Drilling a major contract to carry out a two-well drilling programme at its Cross Lanes Geothermal Lithium Project near Truro, Cornwall.
The appointment marks a significant milestone in the company’s effort to establish a commercially viable, domestically sourced lithium supply chain for the United Kingdom.
Marriott Drilling, based in Chesterfield, Derbyshire, will provide specialist geothermal drilling services for two appraisal wells, each designed to reach approximately 2,000 metres. Drilling is expected to begin in December 2026 and continue for several months, with the programme intended to test whether lithium can be commercially extracted from naturally occurring geothermal brines deep beneath Cornwall.
The contract is more than a routine drilling award. It represents a convergence of Cornwall’s geological heritage, advanced geothermal technology, UK industrial strategy, and the growing global demand for battery materials. If successful, Cross Lanes could become the first stage in a network of modular geothermal lithium production hubs across Cornwall.
The Cross Lanes Project
The Cross Lanes Geothermal Lithium Project is located near Truro and is designed to confirm the commercial viability of producing lithium from geothermal waters, or brines, found deep underground. These waters contain dissolved lithium, a critical raw material for batteries used in electric vehicles, consumer electronics, renewable energy storage, and advanced manufacturing.
The project builds on an exploration borehole drilled at the site in 2023, which successfully tested the presence of lithium-bearing geothermal fluids. The new two-well programme will now move the project from early exploration toward appraisal, providing the data needed to assess whether production can be scaled up.
Each well is expected to reach a target depth of around 2,000 metres. At that depth, the project aims to access geothermal brines at sufficient temperature and volume to support both lithium extraction and potential geothermal energy generation.
Marriott’s Role
Marriott Drilling has been appointed to provide the drilling rig, specialist equipment, and highly skilled personnel with experience in deep geothermal operations. The company will undertake the drilling of the two appraisal wells, working alongside Halliburton, which was previously appointed to provide subsurface modelling, well engineering, and integrated drilling and testing services.
Marriott Drilling Group describes itself as the UK’s largest onshore deep drilling company. It operates more than 25 drilling and workover rigs and provides services to the geothermal, water, mining, oil and gas, and specialist geoscientific sectors in the UK, Europe, and selected international markets.
The company’s expertise is particularly relevant to Cross Lanes. Deep geothermal drilling requires specialist knowledge of high-temperature environments, complex subsurface conditions, well design, and the safe handling of pressurised fluids. Marriott’s experience across multiple drilling disciplines gives Cornish Lithium access to proven operational capability as the project moves into a more demanding phase.
Why Geothermal Lithium Matters
Lithium is central to the modern energy transition. It is a key component of lithium-ion batteries, which power electric vehicles, mobile devices, grid-scale storage systems, and many other technologies essential to decarbonisation.
The UK currently depends heavily on imported critical minerals, including lithium. Developing a domestic source could reduce exposure to international supply-chain disruption, strengthen energy security, and support the growth of British battery manufacturing and advanced manufacturing industries.
Cornish Lithium’s approach is distinctive because it seeks to extract lithium from geothermal brines rather than relying solely on conventional hard-rock mining. This could allow lithium production to be combined with geothermal heat or power generation, potentially creating a more integrated and lower-impact industrial model.
Direct Lithium Extraction
A central element of the Cross Lanes programme is the planned demonstration-scale Direct Lithium Extraction, or DLE, plant. The drilling programme will enable Cornish Lithium to evaluate its preferred lithium extraction technology using brines brought to the surface from the deep geothermal system.
DLE technologies are designed to selectively extract lithium from brines while reducing the need for large evaporation ponds, which are commonly associated with traditional lithium extraction in some parts of the world. The demonstration plant will allow Cornish Lithium to test how effectively its chosen process performs under real operating conditions.
The results will be crucial. They will help determine lithium recovery rates, water usage, energy requirements, processing costs, and the overall commercial feasibility of the project.
Informing Investment Decisions
Data gathered from the drilling programme and the demonstration-scale DLE plant will inform a final investment decision for the Cross Lanes Geothermal Lithium Project. This decision will determine whether the project progresses from appraisal and demonstration toward full-scale development.
The programme is therefore not simply about drilling two wells. It is about generating the technical, operational, and economic evidence needed to justify a major capital investment. The wells will provide information on reservoir characteristics, brine chemistry, flow rates, temperature, and lithium concentration.
If the results are positive, Cross Lanes could become the first stage of Cornish Lithium’s plan to establish a network of modular geothermal lithium production hubs across Cornwall.
Public Funding and Industrial Strategy
The Cross Lanes Geothermal Lithium Project is supported by a £7.2 million grant through the UK Government’s DRIVE35 programme. Cornish Lithium is matching this funding as part of a wider £14.5 million drilling and testing programme.
DRIVE35 reflects the UK Government’s interest in strengthening domestic critical-mineral supply chains and supporting technologies that can underpin the transition to zero-emission transport and renewable energy. The funding signals that Cross Lanes is viewed not only as a private commercial project but also as part of a broader national industrial strategy.
The £14.5 million programme covers drilling and testing activities that will help establish whether Cornwall’s geothermal brines can support commercial lithium production. Public support reduces some of the financial risk associated with early-stage innovation, while Cornish Lithium’s matching investment demonstrates private-sector commitment to the project.
Cornwall’s Lithium Opportunity
Cornwall has a long history of mining and industrial innovation, particularly in tin and copper. The region’s geology also contains lithium-bearing minerals and geothermal resources, creating an opportunity to develop new forms of critical-mineral production.
Cornish Lithium’s broader strategy includes the Trelavour Lithium Project, which will extract lithium from hard rock. Together, geothermal brine extraction and hard-rock lithium production could create a more diverse domestic lithium supply base.
The company aims to produce 20,000 tonnes per annum of scalable and secure lithium for UK industry through its combined projects. This target reflects the scale of demand expected from battery manufacturing, electric vehicles, renewable energy storage, and other advanced technologies.
A Two-Track Lithium Strategy
Cornish Lithium’s approach combines two complementary sources of lithium: geothermal brines and hard rock.
The Cross Lanes project focuses on naturally occurring geothermal brines found deep underground. It involves two appraisal wells and a Direct Lithium Extraction demonstration plant, positioning it as the first stage of a planned network of modular geothermal lithium hubs in Cornwall.
The Trelavour Lithium Project, meanwhile, will extract lithium from hard rock. It represents a more conventional production route but is equally important to Cornish Lithium’s ambition to create a major domestic lithium supply.
Together, the two projects share a common objective: strengthening the UK’s access to secure, scalable lithium. By pursuing both geothermal brine extraction and hard-rock extraction, Cornish Lithium reduces reliance on any single method and creates a more resilient supply strategy.
The Importance of Local Delivery
The appointment of Marriott Drilling also has a regional and national industrial significance. Rather than relying entirely on overseas contractors, Cornish Lithium is using UK-based drilling expertise to deliver a strategically important project.
Marriott’s Chesterfield base and UK operations mean that specialist skills, equipment, and supply-chain activity can remain within Britain. This supports the wider objective of building domestic industrial capability around critical minerals, geothermal energy, and advanced manufacturing.
For Cornwall, the project could also create opportunities for local employment, skills development, and supply-chain participation. While the immediate contract is focused on drilling, successful development could lead to longer-term activity in construction, operations, maintenance, engineering, environmental monitoring, and processing.
Challenges Ahead
The Cross Lanes project still faces important challenges. Deep geothermal drilling is technically complex, and the commercial viability of lithium extraction depends on more than the presence of lithium in brines.
Key questions include whether the wells can deliver sufficient flow rates, whether lithium concentrations are high enough, whether extraction technology can operate efficiently at scale, and whether the overall economics support a final investment decision. The demonstration-scale DLE plant is designed specifically to answer many of these questions.
Environmental management, community engagement, water use, and regulatory compliance will also be important. As with any mining or energy project, public confidence will depend on transparent consultation, responsible operations, and clear evidence of local benefit.
A Test Case for the UK
Cross Lanes is emerging as a major test case for whether the UK can develop a domestic lithium industry using innovative geothermal technology. The project combines public funding, private investment, local geology, specialist drilling expertise, and advanced extraction technology.
If successful, it could demonstrate that lithium can be produced in Britain from geothermal brines while potentially supporting renewable energy production. That would be a significant achievement for Cornwall, for the UK battery supply chain, and for the country’s wider industrial strategy.
Even if the project does not proceed immediately to full commercial production, the data and experience generated will be valuable. The drilling programme will improve understanding of Cornwall’s deep geothermal resources and provide practical evidence on the performance of DLE technology.
Looking Ahead
Drilling is expected to begin in December 2026 and continue for several months. During that period, Marriott Drilling will deliver the physical infrastructure needed to access and test the geothermal brines beneath Cross Lanes.
The next stage will focus on analysing the results, operating the demonstration-scale DLE plant, and assessing whether the project can meet the technical and commercial requirements for a final investment decision.
For Cornish Lithium, Marriott Drilling, Halliburton, and the UK Government, the project represents a coordinated effort to turn geological potential into industrial reality. For the UK, it could be an important step toward a more secure, resilient, and domestically anchored lithium supply chain.
Source: Cornish Lithium