Quaise’s Google PPA

Quaise Signs a PPA With Google: A Major Test for Superhot Geothermal Quaise Energy has signed a 50-megawatt power purchase agreement with Google for electricity from Project Obsidian, the company’s flagship superhot geothermal development in Central Oregon. The deal is one of the clearest signs yet that next-generation geothermal is moving from a promising concept into a commercial energy business. Under the agreement, Google will begin purchasing 50 MW of power from Project Obsidian as early as 2030. The electricity is intended to support Google’s existing data-center operations in The Dalles, Oregon, while also contributing to the wider regional energy system. For Quaise, the agreement provides something every early-stage energy developer needs: a credible buyer. For Google, it adds another source of firm, carbon-free electricity at a time when artificial intelligence, cloud computing, and expanding data centers are sharply increasing demand for reliable power. What the Agreement Mea...

Quaise’s Google PPA

Quaise Signs a PPA With Google: A Major Test for Superhot Geothermal

Quaise Energy has signed a 50-megawatt power purchase agreement with Google for electricity from Project Obsidian, the company’s flagship superhot geothermal development in Central Oregon. The deal is one of the clearest signs yet that next-generation geothermal is moving from a promising concept into a commercial energy business.

Under the agreement, Google will begin purchasing 50 MW of power from Project Obsidian as early as 2030. The electricity is intended to support Google’s existing data-center operations in The Dalles, Oregon, while also contributing to the wider regional energy system.

For Quaise, the agreement provides something every early-stage energy developer needs: a credible buyer. For Google, it adds another source of firm, carbon-free electricity at a time when artificial intelligence, cloud computing, and expanding data centers are sharply increasing demand for reliable power.

What the Agreement Means

A power purchase agreement, or PPA, is a long-term contract in which a buyer agrees to purchase electricity from a specified generation project. In this case, Google is committing to buy power from Quaise’s Project Obsidian, giving the developer a commercial customer for its first phase of production.

The agreement matters because it moves superhot geothermal closer to utility-scale reality. Google’s purchase gives Quaise demand certainty, which can help the company attract investment, secure equipment, expand drilling, and demonstrate that its technology can deliver electricity at commercial scale.

For Google, the PPA is part of a broader strategy to secure clean, reliable energy for its growing infrastructure. Unlike solar and wind, geothermal can operate around the clock. That makes it especially valuable for data centers, which need electricity continuously and cannot tolerate major interruptions in supply.

The 50 MW contract is relatively small compared with Google’s overall electricity needs. But its significance is strategic. It represents a major company placing a commercial bet on a new form of geothermal energy, one that could unlock vastly more power than conventional systems if it succeeds.

Why “Superhot” Matters

Traditional geothermal power relies on naturally occurring reservoirs of hot water or steam that are close enough to the surface to be economically accessible. Those conditions exist in only certain places, which is one reason geothermal remains a small part of global electricity generation despite its potential.

Quaise is pursuing a different approach. Its enhanced geothermal systems, or EGS, are designed to access superhot conditions deep underground, where rock temperatures are far higher than in conventional geothermal fields. By creating or improving permeability in hot rock, EGS can circulate fluid through the formation, capture heat, and bring it to the surface to generate electricity.

Quaise says its approach could generate up to 10 times more clean power per well than traditional geothermal systems. The logic is straightforward: hotter rock contains more usable thermal energy, and higher temperatures can support more efficient power generation.

The company’s central technological bet is millimeter-wave drilling. Rather than relying solely on conventional mechanical drill bits, Quaise is developing a method that uses high-frequency electromagnetic energy to vaporize or break apart rock at extreme depths. The goal is to reach superhot formations that conventional drilling cannot access economically.

If that technology works as intended, it could dramatically expand the number of places where geothermal power can be developed. Instead of limiting geothermal to a handful of naturally favorable regions, developers could potentially access deep heat resources in many parts of the world.

Project Obsidian’s Phased Plan

Project Obsidian is designed to prove the technology in stages. The initial phase will use conventional drilling methods to reach superhot geothermal conditions at commercial scale. This is a pragmatic approach because it allows Quaise to establish production and deliver power to Google before its most advanced drilling technology is fully deployed.

The second phase is expected to be the first in the world to use millimeter-wave drilling. Quaise says this technology will enable access to deeper rock layers, increasing Project Obsidian’s capacity to 250 MW.

A potential third phase could expand the project beyond 1 GW. If achieved, that would place Project Obsidian among the largest geothermal developments ever built and would demonstrate that superhot geothermal can move beyond pilot projects to become a meaningful contributor to regional power supply.

That expansion path matters because electricity systems need more than isolated demonstration plants. They need projects that can be replicated, financed, interconnected, and operated reliably for decades. Google’s PPA gives Quaise a commercial anchor for that process.

Google’s Data-Center Strategy

Google has operated in Oregon since 2006, when it opened its first owned-and-operated data center in The Dalles. Today, the company operates three data-center campuses in the city, along with a Google Cloud region in Oregon and an office in downtown Portland.

The company says its Oregon data centers have already reached 83% carbon-free energy. The Quaise agreement is intended to extend that progress by adding a source of power that is both clean and continuously available.

Google says it pays for 100% of the electricity used by its data centers and covers infrastructure needs directly driven by its growth. That distinction is increasingly important as AI workloads expand and communities ask whether large technology companies are adding demand without paying for the generation and grid capacity needed to serve it.

In that context, geothermal has a particular appeal. Solar and wind are essential to decarbonization, but their output varies with weather and time of day. Data centers require reliable power every hour, and geothermal can provide baseload generation that complements intermittent renewables rather than depending on them.

A Broader Clean-Energy Portfolio

The Quaise deal is not Google’s first move into geothermal. The company says that from 2010 through 2025, it signed more than 240 agreements to purchase nearly 35 GW of new clean energy, including more than 29 GW in North America across 148 projects.

Google has also signed a 396 MW PPA with enhanced-geothermal developer Fervo Energy in Utah, a 150 MW conventional geothermal PPA with Ormat Technologies in Nevada, and a 10 MW geothermal agreement with Baseload Capital in Taiwan.

Those agreements show that Google is treating geothermal as more than a symbolic climate commitment. The company is building a portfolio of firm clean-power resources that can support data-center growth while reducing reliance on fossil generation.

The Quaise agreement is also Google’s second PPA this year with an EGS developer. That repetition matters because early-stage energy technologies often need multiple credible buyers before they can attract broad investment and achieve lower costs through repetition.

Why Hyperscalers Are Turning to Geothermal

Google is not alone. Meta has signed offtake agreements with two U.S. EGS developers, including a 150 MW agreement with Sage Geosystems for a project east of the Rocky Mountains and a 150 MW agreement with XGS Energy for a project in New Mexico.

Microsoft has also entered the field. In 2023, it signed a ten-year PPA with Contact Energy for 51 MW in New Zealand, and it has partnered with G42 on a data center in Kenya intended to run exclusively on geothermal energy.

The pattern is clear: major technology companies are looking for clean, firm power because their facilities consume electricity continuously and their growth is accelerating. AI training and inference can substantially increase data-center electricity demand, making energy procurement a core part of corporate infrastructure strategy rather than a peripheral sustainability issue.

Geothermal offers several advantages in that environment:

It can deliver around-the-clock output, unlike solar or wind.

It has a relatively small surface footprint compared with many other forms of generation.

It could potentially be developed in many locations if deep-drilling technology becomes economic.

It can provide long-lived infrastructure with predictable operating characteristics.

It can reduce exposure to fuel-price volatility because the heat source is naturally occurring underground heat.

The Economic Case for Oregon

Quaise says Project Obsidian could support 200 to 400 jobs during construction and more than 50 permanent high-skilled jobs in engineering and operations. The company also says the project could establish Central Oregon as a hub for superhot geothermal development.

The project’s grid upgrades are expected to strengthen reliability for local consumers. Royalties from electricity sales could provide longer-term economic benefits to the region.

Google’s presence in The Dalles is already substantial. The company says it has invested more than $7 billion in Oregon over the past 20 years, ranks as the largest taxpayer in Wasco County in recent years, and helped generate $9.3 billion in economic activity in 2025 for Oregon businesses, nonprofits, publishers, creators, and developers.

For local communities, the value of the project will depend on execution. Jobs, tax revenue, grid improvements, and royalties are potential benefits, but they must be weighed against construction impacts, water use, land-use questions, and the need to ensure that local residents share in the project’s economic upside.

The Technology Risk

The most important caveat is that Project Obsidian remains an under-development project. The first phase is expected to use conventional drilling, but the more transformative element of Quaise’s plan—millimeter-wave drilling—has still to prove itself at the scale required for a 250 MW expansion.

Deep geothermal drilling faces formidable engineering challenges. Rock becomes harder and hotter at depth, equipment must withstand extreme temperatures and pressures, and operators must manage fluid flow, well integrity, seismic risk, and cost control. A technology that works in a test environment does not automatically become a reliable, low-cost power plant.

That is why the Google PPA is meaningful but not a guarantee of success. It provides commercial validation and a pathway to market, but it does not eliminate technical, financial, regulatory, or construction risk.

Quaise itself notes that its announcement contains forward-looking statements and that actual results may differ materially from expectations. That is a reminder that energy innovation often takes longer and costs more than its supporters hope.

What a PPA Does—and Does Not—Guarantee

A PPA is not simply a promise that a power plant will exist. It is a commercial arrangement that can help make a project financeable by giving a developer a buyer for future output. In Quaise’s case, Google’s commitment signals that a sophisticated corporate buyer sees enough promise in the technology to contract for its electricity.

But PPAs typically depend on the project reaching commercial operation. The announced start date of “as early as 2030” is therefore a target, not a certainty. The project must still complete development, drilling, testing, grid interconnection, permitting, financing, and construction before Google can receive power.

The agreement’s real value lies in what it enables: capital formation, operational learning, supply-chain development, and proof that superhot geothermal can produce electricity for a demanding corporate customer. If Project Obsidian succeeds, later projects could become cheaper and easier to finance.

A Test for the Geothermal Industry

The Quaise-Google agreement arrives at a moment of rising interest in next-generation geothermal. Companies such as Fervo, Sage Geosystems, XGS Energy, and Quaise are pursuing different versions of enhanced geothermal, but they share a common objective: unlock heat from rock formations that conventional geothermal cannot reach.

If these technologies succeed, the implications could be substantial. The Earth contains enormous amounts of heat, and unlike solar or wind, that heat is available continuously. The challenge has never been whether geothermal energy exists; it is whether humans can access it affordably, safely, and at scale.

Quaise’s approach is especially ambitious because it targets superhot conditions rather than merely expanding access to moderate-temperature resources. Higher temperatures could enable more power per well, but they also demand more advanced drilling and materials.

The company says its millimeter-wave technology was developed after more than a decade of research at MIT. Its stated mission is to make superhot geothermal the backbone of a modern energy system, offering affordable, zero-carbon power and greater energy independence.

The AI Electricity Problem

The timing of the deal is not accidental. AI is driving a new wave of data-center construction, and those facilities require large volumes of electricity with high reliability. Companies that once focused mainly on buying renewable energy certificates are now directly contracting for new generation capacity.

Google’s language reflects that shift. The company says it remains committed to ensuring that energy is affordable, reliable, and accessible for families and businesses as national electricity demand grows.

That creates an opportunity for geothermal developers, but also a responsibility. If hyperscalers procure large volumes of clean power, they can accelerate deployment of low-carbon generation. But they must also ensure that new data-center demand does not simply shift costs onto local ratepayers or strain grids without adequate investment in transmission, storage, efficiency, and community engagement.

Google says it covers infrastructure needs directly driven by its growth, a statement intended to address that concern. The practical test will be whether projects such as Project Obsidian deliver benefits that are broadly shared rather than concentrated among developers and large corporate buyers.

Why This Deal Could Be a Turning Point

The Quaise-Google PPA is notable for three reasons.

First, it is a commercial-scale commitment to superhot geothermal, a technology that has long promised enormous potential but has yet to prove itself across a full utility-scale project.

Second, it links that technology directly to one of the world’s most power-hungry industries. Data centers need firm clean power, and Google’s willingness to contract for 50 MW gives Quaise a tangible commercial pathway.

Third, it creates a replicable model. If Project Obsidian delivers power on schedule and at competitive cost, other developers, utilities, and corporate buyers may be more willing to finance similar projects.

The deal will not solve the world’s energy challenges on its own. Fifty megawatts is a small fraction of the generation needed to decarbonize electricity systems or meet surging AI demand. But first commercial projects often matter disproportionately because they establish technical credibility, reduce perceived risk, and create the supply chains needed for later growth.

The Road to 2030

Between now and the expected start of deliveries, Quaise must demonstrate that it can drill, complete, test, and operate wells under superhot conditions. It must also build or secure the surface plant, interconnect with the grid, obtain permits, manage construction, and meet the reliability expectations of a buyer such as Google.

The first phase’s use of conventional drilling reduces some near-term technical risk. It allows Quaise to establish a commercial product before relying entirely on millimeter-wave drilling. But the company’s long-term cost and scalability thesis still rests on its ability to make that advanced drilling technology work economically.

If the second phase reaches 250 MW, it would be a much stronger signal that superhot geothermal can scale. If a third phase exceeds 1 GW, Project Obsidian could become a reference project for the entire industry.

Bottom Line

Quaise’s 50 MW PPA with Google is a landmark agreement for superhot geothermal energy. It gives Quaise a major corporate customer, gives Google another source of always-on carbon-free power, and gives the geothermal industry a high-profile test of whether deep-rock energy can become commercially viable.

The agreement does not guarantee that Project Obsidian will succeed, nor does it prove that millimeter-wave drilling will transform global energy markets. But it turns a promising technology into a contracted commercial project with a clear buyer, a delivery target, and a route toward much larger capacity.

If Quaise can deliver power from Project Obsidian by 2030, the deal may be remembered as the moment superhot geothermal moved from an ambitious startup thesis to a credible part of the clean-energy transition. If it struggles, it will still provide valuable evidence about the barriers that remain. Either way, Google’s decision to sign makes the next several years one of the most important testing periods for the future of geothermal power.

Source : Quaise Energy 

Comments

Popular posts from this blog

Green Therma Generation 5 Geothermal Technology Revolutionises Enclosed Loop Heat Production

Green Therma’s Fifth Generation Geothermal Technology Targets Heat Markets Image: Kim Gunn Maver, Chief Geologist at Green Therma The geothermal industry has historically depended on favourable geological conditions, naturally permeable reservoirs and the availability of underground fluids. Although conventional hydrothermal systems have enabled commercial geothermal electricity generation and heat across several countries, their dependence on specific geological characteristics has limited the number of locations where projects can be developed successfully. A new generation of engineered geothermal technologies is seeking to address these limitations by changing how heat is extracted from the subsurface. Green Therma is advancing what it describes as Generation 5 geothermal technology, centred on Enclosed Loop Geothermal (ELG). Unlike conventional hydrothermal systems and Enhanced Geothermal Systems (EGS) , the technology uses a fully enclosed engineered piping arrangement that pre...

Novi Sad Miseluk Geothermal Heating Plant: €7.6 Million District Heating Project

Novi Sad Advances Miseluk Geothermal Heating Plant as Serbia Embraces Low-Carbon District Energy Novi Sad is moving ahead with an ambitious district-heating project that could change how new urban neighborhoods in Serbia are supplied with thermal energy. The city’s public heating utility, JKP Novosadska toplana, has launched a new tender for the design and construction of the Miseluk heating plant, a hybrid facility that will combine geothermal energy, natural gas and solar technology. The procurement is valued at approximately 892.5 million Serbian dinars excluding value-added tax, equivalent to roughly €7.6 million. The project is designed to reach a final heating capacity of up to 30 megawatts and will serve the growing Miseluk area of Novi Sad.  The tender represents a renewed attempt to deliver the project after an earlier procurement procedure was cancelled in September 2026 because all submitted bids were considered unacceptable. Companies participating in the new procedure ...

Germany Advances Rhineland Geothermal Exploration Through Fraunhofer IEG Seismic Survey

Germany Advances Rhineland Geothermal Exploration as Fraunhofer IEG Secures Seismic Survey Approval A Major Step for Geothermal Energy in Germany Germany is advancing its geothermal exploration ambitions in the Rhineland as researchers move closer to understanding the region's deep geological potential. The Fraunhofer Research Institution for Energy Infrastructures and Geotechnologies (Fraunhofer IEG) has secured regulatory approval to conduct a seismic exploration campaign under the Reallabor Geothermie Rheinland (Rhineland Geothermal Real Laboratory), marking an important milestone in efforts to establish geothermal energy as a long-term source of sustainable heat. The approval, granted by the Arnsberg Mining Authority, allows the research team to proceed with preparations for a geophysical measurement campaign covering two profiles with a combined length of approximately 35 kilometres. The proposed survey will investigate the subsurface between Baesweiler, Eschweiler and the H...

Eden Geothermal’s Expansion: Cornwall’s Ambitious Plan for Four More Wells

Eden Geothermal Plans Four More Wells in Expansion of Cornwall Renewable Energy Project Eden Geothermal has proposed drilling four additional underground wells at its site near the Eden Project in Cornwall, potentially increasing the total number of wells from two to six. The company says the changes could substantially increase renewable heat and power generation without expanding beyond the development boundary or fundamentally changing the scheme already approved by Cornwall Council.  The proposal represents an important test for the future of deep geothermal energy in the United Kingdom. Geothermal power is often associated with volcanic regions such as Iceland, Kenya, Indonesia and New Zealand, but the Eden project relies on the heat stored deep beneath Cornwall’s granite. If the expansion succeeds, it could demonstrate how naturally occurring underground heat can provide dependable low-carbon energy in countries where conventional geothermal resources are less obvious. At the...

Geothermal Data Centers: Rewriting the Water-Energy Equation

Thirsty Servers, Silent Reservoirs: Can Geothermal Power the Water-Smart Data Center Era? By: Robert Buluma The digital economy runs on an invisible infrastructure—rows of servers humming inside vast data centers, processing everything from financial transactions to artificial intelligence models. But beneath this digital revolution lies a growing, often overlooked tension: water . Recent projections warn that data centers could consume as much freshwater as tens of millions of people by 2030 . Whether the exact figure is 30, 40, or 46 million, the signal is unmistakable: the world’s data infrastructure is becoming a major water consumer . At the same time, a quieter force is emerging from beneath the Earth’s surface— geothermal energy —with the potential not only to power data centers, but to fundamentally reshape their water footprint . This is not just a story about energy. It is a story about resource convergence —where water, heat, electricity, and digital demand collide—and ho...

LCOE Benchmarking: Eavor Technologies vs. Fervo Energy

LCOE Compared: Eavor Technologies vs.  Fervo Energy   Two Bets on Next-Generation Geothermal An Alphaxioms Geothermal Insights Analysis | May 2026 Image:  Eavor and Fervo Drilling Rigs well poised in their respective well pads , drill baby , baby what a time to be a live Introduction: Why the Cost Question Matters Now The global geothermal sector is in the middle of a pivotal moment. After decades of stagnation largely confined to volcanic hotspots, two fundamentally different technological approaches are racing to prove that geothermal energy can be deployed broadly, cheaply, and at scale. Eavor Technologies , the Calgary-based advanced geothermal systems (AGS) company, and Fervo Energy , the Houston-based enhanced geothermal systems (EGS) pioneer, represent the sharpest divergence in next-generation geothermal strategy today. Each company is backed by hundreds of millions of dollars in private capital, each has reached key commercial milestones, and each is advancing ...

Project Obsidian: Unlocking Superhot Geothermal Power from Deep Earth

Quaise Energy and the Dawn of Superhot Geothermal Power in Oregon By: Robert Buluma Inside Project Obsidian and the Future of Deep Earth Energy The global energy transition has long been defined by solar panels on rooftops, wind turbines across plains, and batteries reshaping grids. Yet beneath all these familiar technologies, another contender is quietly emerging—one that does not depend on weather, daylight, or even surface conditions at all. It comes from deep within the Earth itself, from rock so hot it behaves almost like a molten energy reservoir. That is the frontier where Quaise Energy is now operating. In Oregon, the company is developing what could become the world’s first superhot geothermal power plant under its ambitious initiative known as Project Obsidian . If successful, it could mark a fundamental shift in how humanity produces clean, continuous electricity—moving from shallow geothermal pockets to tapping heat sources several kilometers beneath the Earth’s surfac...

Vigil Against Varto Geothermal Power Plant Continues Amid Rising Environmental and Community Concerns

Vigil Against Geothermal Power Plant in Varto Continues: A Struggle Between Energy Transition and Local Survival Introduction: When Clean Energy Meets Local Resistance In the highlands of eastern Turkey, in the district of Varto (also known as Gimgim), a quiet but powerful resistance is unfolding. Villagers have set up tents, organized rallies, and launched legal action against a planned geothermal power plant project that they fear could permanently alter their environment, livelihoods, and cultural landscape. While geothermal energy is widely promoted as a clean and renewable energy source, the case of Varto highlights a growing global tension: Can renewable energy projects still cause environmental and social harm at the local level? Since early 2026, the region has witnessed continuous protests, legal challenges, and a persistent sit-in vigil by residents opposing exploration and drilling activities scheduled for the area. The Project at the Center of the Conflict The contest...

"Olkaria: Africa's Geothermal Giant, Still Searching for Synergy"

Olkaria Geothermal Field: Africa’s Energy Giant With Untapped Billions Beneath Deep within Kenya’s Great Rift Valley lies a geothermal powerhouse that has quietly redefined Africa’s energy landscape—Olkaria Geothermal Field. For decades, Olkaria has stood as a symbol of resilience, innovation, and baseload stability in a continent long challenged by energy insecurity. But here’s the uncomfortable truth:   Olkaria is not yet operating at its full potential. Beneath its steam fields, pipelines, and turbines lies a far more complex, under-optimized system—one that, if properly engineered and integrated, could unlock billions of dollars in additional value beyond electricity generation. This is not just a story about megawatts.   This is a story about missed integration, untapped resources, and the next frontier of geothermal dominance. 1. The Scale of Olkaria — Impressive, Yet Fragmented Olkaria is one of the largest geothermal complexes in the world, with Kenya’s total...

The Retrofit Revolution: How GreenFire Energy Is Turning Abandoned Oil & Geothermal Wells Into Continuous Clean Power Without New Drilling

The Retrofit Revolution: How GreenFire Energy Is Unlocking Geothermal Power Without Drilling a Single New Well By: Robert Buluma   While much of the geothermal energy sector has been focused on breakthrough drilling techniques—deeper wells, hotter reservoirs, and complex engineered systems—a quieter revolution has been unfolding in the background. Instead of chasing entirely new subsurface frontiers, one company has chosen a radically simpler question: What if the answer was already in the ground? GreenFire Energy is advancing a retrofit-first geothermal strategy that targets one of the most overlooked opportunities in the global energy transition: existing wells that are underperforming, depleted, or completely abandoned. Rather than drilling new holes into the Earth, the company is reusing the infrastructure that already exists—turning stranded assets into continuous sources of clean, baseload electricity. This approach is not just technically elegant. It may also be one of ...